Asset Register
|
Work Name
|
(3305005014/RS/1111376305) SAMUDAYIK SHOUCHALAY NIRMAN KOYLARI |
Nature of Work |
|
Work Status
|
Completed
|
Work Purpose status
|
Construction of Multi Unit Toilets for School |
Scope of Work
|
|
Sanction No. and Sanction Date
: 3033/1 ,
29/10/2020
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: No |
Estimated Cost (In Lakhs)
:
3.5
|
Estimated Completion Time (in Months)
|
8 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
56255 |
0 |
0 |
0 |
0 |
56255 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
293 |
58 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
33501(11970),34826(190),35744(190),36572(3990),36866(2280), 256(5404),2072(5404),3277(1351),3283(2702),3284(1351), 4058(3667),4059(2702),4942(193),4944(193),5146(2702), 5195(8106),6581(3474),6582(193),6846(193),
|
Work start date |
08/03/2021 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|