Asset Register
|
Work Name
|
(2412001014/WC-Tank/44579) Digging of New Bandha |
Nature of Work |
Water Conservation
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Derelict |
Desilting |
|
Location
|
|
Sanction No. and Sanction Date
: FS/GAN/SAS/GP ,
16/02/2008
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
5
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
0 |
0 |
0 |
0 |
0 |
0 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
3186 |
229 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
259753(10360),259754(9800),259755(9800),259756(9800),259757(9800), 259758(9800),259759(9800),259760(9800),259761(9800),259762(9800), 259763(9800),259764(0),259765(0),259766(0),259769(0), 259770(0),259772(0),259773(0),259774(0),259775(8750), 259776(0),200621(0),200622(0),200623(0),
|
Work start date |
20/02/2008 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|