Asset Register
|
Work Name
|
(2420009018/RC-Sand Moram/99421) Damasahi to Sethysahi road,Mirzapurbothsideearthfilling, |
Nature of Work |
Rural Connectivity
|
|
Completed
|
Work Purpose status
|
Sand Moram |
Scope of Work
|
Start Status |
End Status |
No Road |
Sand Moram |
|
Location
|
Start Location |
End Location |
|
Mirzapur |
Khata No. |
Plot No. |
/ |
/ |
|
Sanction No. and Sanction Date
: R/018/23 ,
30/01/2010
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
2.5
|
Estimated Completion Time (in Months)
|
1 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
0 |
0 |
0 |
0 |
0 |
0 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1346 |
280 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
40963(5460),40964(5460),40965(5460),40966(5460),40967(5460), 40968(5460),40969(5460),40970(6000),40971(6000),40972(6000), 40973(6000),40974(6000),40975(6000),40976(6000),40977(6000), 40978(6000),40979(6000),40980(6000),40981(6000),40982(6000), 40983(6000),40984(1800),40985(1440),40986(900),40987(900), 40988(900),40989(900),40990(900),
|
Work start date |
09/03/2010 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|