Asset Register
|
Work Name
|
(2412010/AV/10377907) Poirasi / Const. of AWC Building Bhuainbhuin 3 near Bada Kuan at Bhuanbhuin 2019 / 20 |
Nature of Work |
|
|
Completed
|
Work Purpose status
|
Constr of Anganwadi for community |
Scope of Work
|
|
Sanction No. and Sanction Date
: 2412010/2019-2020/82939/AS ,
30/11/2019
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
5
|
Estimated Completion Time (in Months)
|
3 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
78396 |
32046 |
27832 |
355504 |
0 |
493778 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
417 |
61 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
12548(2632),14875(11844),14876(5264),6435(11844),6436(4136), 11790(7896),14920(13160),15103(13160),20251(8460),
|
Work start date |
19/02/2020 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|