Asset Register
|
Work Name
|
(2412016022/RC-Sand Moram/7322) Imp of road from Sunaribada Chhaka to Daleibila |
Nature of Work |
Rural Connectivity
|
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Earthern road |
Sand Moram |
|
Location
|
Start Location |
End Location |
|
DALEI BILA |
Khata No. |
Plot No. |
11/14 |
11/14 |
|
Sanction No. and Sanction Date
: FS0019 ,
01/07/2006
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
2.85
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
177085 |
0 |
900 |
58559 |
0 |
236544 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
3211 |
268 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
11530(6600),11531(5940),11532(6600),11533(6325),11534(6600), 11535(6600),11536(6600),11610(7260),11611(5940),11612(6840), 11613(6600),11614(6600),11615(6600),11616(6600),11617(6600), 11618(6180),11619(6600),11620(6600),11621(6600),11622(6600), 11623(6600),11624(6600),11625(6600),11626(6600),11627(7920), 11628(5280),11629(6600),
|
Work start date |
03/07/2006 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|