S.No District Block Gram Panchayat Work Name (Work Code) Executing Level Completion Date (DD/MM/YYYY) Est. labour component(in RS.) Est. material component(in RS.) Actual exp. on labour(in RS.) Actual exp. on material(in RS.)
ODISHA
1DEOGARH TILEIBANI BADCHAPAL LBCD at Kuturapasi  (2416001001/WC/10495350) GP 31/03/2023 63477.5 21807.42 61494 12600
2  TILEIBANI BADCHAPAL LBCD at Tirib  (2416001001/WC/10495348) GP 25/05/2022 63477.5 21807.42 69660 5000
3  TILEIBANI BADCHAPAL TRENCH CUM FIELD BUNDING  (2416001001/WC/10435991) GP 31/10/2022 183668.94 16331.06 177036 13424
4  TILEIBANI BADCHAPAL Trench cum field bunding at Baburikani  (2416001001/WC/10495346) GP 31/10/2022 196356.37 17643.63 186036 17636
5  TILEIBANI BADCHAPAL Trench cum field bunding at Subarnapali  (2416001001/WC/10495349) GP 10/07/2022 196356.37 17643.63 177590 17643
6  TILEIBANI BADCHAPAL TRENCH CUM FIELD BUNDING AT BICHHANAPUR  (2416001001/WC/10495363) GP 31/10/2022 196614.06 18385.94 180560 13424
7  TILEIBANI BADCHAPAL TRENCH CUM FIELD BUNDING AT BADCHHAPAL  (2416001001/WC/10495377) GP 18/10/2022 196614.06 18385.94 89440 0
8  TILEIBANI BADCHAPAL STAGGERED /CONTOUR TRENCH BHULKABAHAL  (2416001001/WC/10435990) GP 31/10/2022 281051.52 18948.47 253524 18424
9  TILEIBANI BADCHAPAL IMPROVEMENT OF BABURIKANI KENDUBHADI KATA  (2416001001/WC/10406102) GP 31/10/2022 279469 14394.6 126120 5000
10  TILEIBANI BADCHAPAL Stragged trench at Baburikani  (2416001001/WC/10495344) GP 25/05/2022 284459.44 18540.56 239940 13352
11  TILEIBANI BADCHAPAL Stragged trench at Subarnapali  (2416001001/WC/10495352) GP 31/03/2023 284459.44 18540.56 118680 9176
12  TILEIBANI BADCHAPAL Stragged trench at Tirib  (2416001001/WC/10495354) GP 10/07/2022 284459.44 18540.56 278210 18540
13  TILEIBANI BADCHAPAL Stragged trench at Brahmasadhubahal  (2416001001/WC/10495356) GP 12/12/2022 284459.44 18540.56 168990 13352
14  TILEIBANI BADCHAPAL STRAGGED TRENCH AT BICHHANAPUR  (2416001001/WC/10495359) GP 31/10/2022 284459.44 18540.56 242528 13424
15  TILEIBANI BADCHAPAL STRAGGED TRENCH AT GINAHAJA  (2416001001/WC/10495361) GP 30/03/2023 284832.8 19167.2 92880 0
16  TILEIBANI BADCHAPAL STRAGGED TRENCH AT BADCHHAPAL  (2416001001/WC/10495400) GP 30/03/2023 284459.44 18540.56 175870 13352
17  TILEIBANI BANIAKILINDA LBCD AT GAJURIBANI  (2416001002/WC/10502520) GP 08/08/2022 63477.5 23807.42 64930 32336
18  TILEIBANI BANIAKILINDA TRENCH CUM FIELD BUNDING AT SUNAMUNDA  (2416001002/WC/10496228) GP 15/10/2022 196356.37 17643.63 190242 9176
19  TILEIBANI BANIAKILINDA TRENCH CUM FIELD BUNDING AT BANIAKILINDA  (2416001002/WC/10496235) GP 30/03/2023 196356.37 17643.63 154290 17600
20  TILEIBANI BANIAKILINDA TRENCH CUM FIELD BUNDING AT BRAJAMOHANPUR  (2416001002/WC/10496236) GP 30/03/2023 196356.37 17643.63 78690 9212
21  TILEIBANI BANIAKILINDA TRENCH CUM FIELD BUNDING AT PUDAPADA  (2416001002/WC/10496238) GP 30/09/2022 196356.37 17643.63 196000 9176
22  TILEIBANI BANIAKILINDA TRENCH CUM FIELD BUNDING AT PALSAKUDAR  (2416001002/WC/10496240) GP 30/09/2022 196356.37 17643.63 190236 5000
23  TILEIBANI BANIAKILINDA STAGGERED TRENCH AT SUNAMUNDA  (2416001002/WC/10496201) GP 30/09/2022 284459.44 18540.56 271510 13352
24  TILEIBANI BANIAKILINDA STAGGERED TRENCH AT BANIAKILINDA  (2416001002/WC/10496203) GP 30/03/2023 284459.44 18540.56 187716 17600
25  TILEIBANI BANIAKILINDA STAGGERED TRENCH AT PALSAKUDAR  (2416001002/WC/10496207) GP 30/09/2022 284459.44 18540.56 280980 13352
26  TILEIBANI BANIAKILINDA STAGGERED TRENCH AT NIKTIMAL  (2416001002/WC/10496213) GP 30/03/2023 284459.44 18540.56 256188 13400
27  TILEIBANI BANIAKILINDA STAGGERED TRENCH AT PUDAPADA  (2416001002/WC/10496217) GP 30/08/2022 284459.44 18540.56 252874 13352
28  TILEIBANI BANIAKILINDA STAGGERED TRENCH AT KALAMATI  (2416001002/WC/10496219) GP 30/09/2022 284459.44 18540.56 188244 9176
29  TILEIBANI BANIAKILINDA IMPROVEMENT OF BRAJAMOHANPUR KATA  (2416001002/WC/10475425) GP 25/08/2022 380013.3 113558.44 196080 9176
30  TILEIBANI CHEPLIPALI TRENCH CUM FIELD BONDING AT BRAHMUNIDEI  (2416001003/WC/10497620) GP 06/03/2023 180064.8 17935.2 177600 0
31  TILEIBANI CHEPLIPALI LBCD AT KADALIPAL  (2416001003/WC/10496928) GP 01/11/2022 207870.8 46578.52 201240 66248
32  TILEIBANI CHEPLIPALI STAGGERED TRENCH AT KADALIPAL  (2416001003/WC/10496635) GP 06/03/2023 284459.44 18540.56 276548 9176
33  TILEIBANI CHEPLIPALI STAGGERED TRENCH AT KADAMDARHA COLONY  (2416001003/WC/10496681) GP 31/07/2022 284459.44 18540.56 274340 9176
34  TILEIBANI CHEPLIPALI STAGGERED TRENCH AT KAMAMUNDA  (2416001003/WC/10496683) GP 31/07/2022 284459.44 18540.56 280360 13352
35  TILEIBANI CHEPLIPALI IMP OF RANGAMATIA PURUNA KATA  (2416001003/WC/10477247) GP 30/11/2022 464810.87 30189.14 377844 8352
36  TILEIBANI DHOLPADA TRENCH-CUM-FIELD BUNDING AT- BIJANALI  (2416001004/WC/10437613) GP 01/11/2022 174922.8 20051.6 175440 13424
37  TILEIBANI DHOLPADA TRENCH-CUM-FIELD BUNDING AT- CHANDRAPUR  (2416001004/WC/10437614) GP 01/11/2022 174922.8 20051.6 175440 13424
38  TILEIBANI DHOLPADA TRENCH-CUM-FIELD BUNDING AT- DHOLPADA  (2416001004/WC/10437615) GP 01/11/2022 174922.8 20051.6 174915 13112
39  TILEIBANI DHOLPADA TRENCH-CUM-FIELD BUNDING AT- HETKHAMAR(KADAGUDA)  (2416001004/WC/10437617) GP 01/11/2022 174922.8 20051.6 164136 9212
40  TILEIBANI DHOLPADA TRENCH-CUM-FIELD BUNDING AT- MAJHIPALI  (2416001004/WC/10437620) GP 01/11/2022 174922.8 20051.6 175440 13424
41  TILEIBANI DHOLPADA TRENCH-CUM-FIELD BUNDING AT- MENJARIBAHAL  (2416001004/WC/10437621) GP 01/11/2022 174922.8 20051.6 174708 13112
42  TILEIBANI DHOLPADA TRENCH-CUM-FIELD BUNDING AT- NIRGUNIPALI  (2416001004/WC/10437622) GP 01/11/2022 174922.8 20051.6 178020 13112
43  TILEIBANI DHOLPADA IMP.OF MENJARIBAHAL RAJA KATA  (2416001004/WC/10365676) GP 01/11/2022 277325.84 17674.97 279426 13424
44  TILEIBANI DHOLPADA STAGGERED/CONTOUR TRENCH AT- BIJANALI  (2416001004/WC/10437603) GP 01/11/2022 273973.05 21041.15 277794 0
45  TILEIBANI DHOLPADA STAGGERED/CONTOUR TRENCH AT- CHANDRAPUR  (2416001004/WC/10437604) GP 01/11/2022 273973.05 21041.15 274860 0
46  TILEIBANI DHOLPADA STAGGERED/CONTOUR TRENCH AT- DHOLPADA  (2416001004/WC/10437605) GP 01/11/2022 273973.05 21041.15 274068 13112
47  TILEIBANI DHOLPADA STAGGERED/CONTOUR TRENCH AT- KALIAKHAMAR  (2416001004/WC/10437608) GP 01/11/2022 273973.05 21041.15 274068 0
48  TILEIBANI DHOLPADA STAGGERED/CONTOUR TRENCH AT- KUMURAPALI  (2416001004/WC/10437609) GP 01/11/2022 273973.05 21041.15 274068 0
49  TILEIBANI DHOLPADA STAGGERED/CONTOUR TRENCH AT- MAJHIPALI  (2416001004/WC/10437610) GP 01/11/2022 273973.05 21041.15 275724 0
50  TILEIBANI DHOLPADA STAGGERED/CONTOUR TRENCH AT- MENJARIBAHAL  (2416001004/WC/10437611) GP 01/11/2022 273973.05 21041.15 280692 13112
51  TILEIBANI DHOLPADA STAGGERED/CONTOUR TRENCH AT- NIRGUNIPALI  (2416001004/WC/10437612) GP 01/11/2022 273973.05 21041.15 279450 17168
52  TILEIBANI DHOLPADA STAGGERED TRENCH AT JANAMNALI  (2416001004/WC/10495772) GP 31/10/2022 284459.44 18540.56 294120 9212
53  TILEIBANI DHOLPADA STAGGERED TRENCH AT BHALUDARI  (2416001004/WC/10495773) GP 01/11/2022 284459.44 18540.56 289820 9212
54  TILEIBANI DHOLPADA STAGGERED TRENCH AT GAYAPALI  (2416001004/WC/10495768) GP 01/11/2022 284459.44 18540.56 288960 9212
55  TILEIBANI DHOLPADA STAGGERED TRENCH AT PATHARNALI  (2416001004/WC/10495780) GP 01/11/2022 284459.44 18540.56 283008 9212
56  TILEIBANI DHOLPADA STAGGERED TRENCH AT HATAKATA, JHARNALI  (2416001004/WC/10495782) GP 01/11/2022 284459.44 18540.56 289740 9212
57  TILEIBANI DHOLPADA STAGGERED TRENCH AT PATAKHAMAN  (2416001004/WC/10495787) GP 01/11/2022 284459.44 18540.56 289260 9212
58  TILEIBANI DHOLPADA Imp of Gayapali Bandha  (2416001004/WC/10544910) GP 01/11/2022 472904.3 25092.68 479520 11318
59  TILEIBANI DHOLPADA Imp of Majhipali Mundisahi bandha  (2416001004/WC/10544913) GP 01/11/2022 472904.3 25092.68 479520 11318
60  TILEIBANI DIMIRIKUDA TRENCH CUM FIELD BUNDING  (2416001005/WC/10435999) GP 01/07/2022 174922.8 20051.6 152757 24056
61  TILEIBANI DIMIRIKUDA TRENCH CUM FIELD BUNDING  (2416001005/WC/10436001) GP 01/07/2022 174922.8 20051.6 174150 6318
62  TILEIBANI DIMIRIKUDA STAGGERED/CONTOUR TRENCH  (2416001005/WC/10436004) GP 01/07/2022 273973.05 21041.15 293045 6318
63  TILEIBANI DUDHIANALI TRENCH-CUM-FIELD BUENDING AT- BANKADARH  (2416001006/WC/10437456) GP 02/11/2022 174922.8 20051.6 174708 20025
64  TILEIBANI DUDHIANALI TRENCH-CUM-FIELD BUENDING AT- KANTEIKOLI  (2416001006/WC/10437458) GP 02/11/2022 174922.8 20051.6 176364 20025
65  TILEIBANI DUDHIANALI TRENCH-CUM-FIELD BUENDING AT- KHALINALI  (2416001006/WC/10437459) GP 02/11/2022 174922.8 20051.6 176364 20025
66  TILEIBANI DUDHIANALI TRENCH-CUM-FIELD BUENDING AT- SABARPALI  (2416001006/WC/10437460) GP 02/11/2022 174922.8 20051.6 173880 20025
67  TILEIBANI DUDHIANALI TRENCH-CUM-FIELD BUENDING AT- TALABAHALI  (2416001006/WC/10437461) GP 02/11/2022 174922.8 20051.6 176364 20025
68  TILEIBANI DUDHIANALI STAGGERED/CONTOUR TRENCH AT- BANKADARH  (2416001006/WC/10437466) GP 02/11/2022 273973.05 21041.15 273240 20287
69  TILEIBANI DUDHIANALI STAGGERED/CONTOUR TRENCH AT- JAMBUNALI  (2416001006/WC/10437467) GP 02/11/2022 273973.05 21041.15 273240 20287
70  TILEIBANI DUDHIANALI IMP.OF NUASAHI UPPAR BANDHA  (2416001006/WC/10365678) GP 02/11/2022 277325.84 17674.97 278670 15000
71  TILEIBANI DUDHIANALI IMP.OF MADHYABHUMI KATA  (2416001006/WC/10365679) GP 02/11/2022 277325.84 17674.97 287340 17000
72  TILEIBANI DUDHIANALI IMP.OF TALABAHALI MANDIRA BANDHA   (2416001006/WC/10365680) GP 02/11/2022 277325.84 17674.97 277278 17000
73  TILEIBANI DUDHIANALI STAGGERED/CONTOUR TRENCH AT- KANTEIKOLI  (2416001006/WC/10437468) GP 02/11/2022 273973.05 21041.15 273240 20287
74  TILEIBANI DUDHIANALI STAGGERED/CONTOUR TRENCH AT- KHALINALI  (2416001006/WC/10437469) GP 02/11/2022 273973.05 21041.15 274896 20287
75  TILEIBANI DUDHIANALI STAGGERED/CONTOUR TRENCH AT- SABARPALI  (2416001006/WC/10437470) GP 02/11/2022 273973.05 21041.15 279840 20287
76  TILEIBANI DUDHIANALI STAGGERED/CONTOUR TRENCH AT- TALABAHALI  (2416001006/WC/10437471) GP 02/11/2022 273973.05 21041.15 273240 20287
77  TILEIBANI DUDHIANALI STAGGERED/CONTOUR TRENCH AT- TENTLOI  (2416001006/WC/10437602) GP 02/11/2022 273973.05 21041.15 273240 20287
78  TILEIBANI KANSAR STAGGERED TRENCHES AT KANSAR  (2416001008/WC/10430540) GP 16/10/2022 186301.67 13698.32 172860 0
79  TILEIBANI KANSAR STAGGERED TRENCHES AT PALUNIPADA  (2416001008/WC/10430543) GP 16/10/2022 186301.67 13698.32 147060 0
80  TILEIBANI KANSAR STAGGERED TRENCHES AT LAINDA  (2416001008/WC/10430544) GP 16/10/2022 186301.67 13698.32 175440 0
81  TILEIBANI KANSAR STAGGERED TRENCHES AT HIRAN  (2416001008/WC/10430547) GP 16/10/2022 186301.67 13698.32 173935 0
82  TILEIBANI KANSAR IMP.OF TELABHANGUNI BANDHA  (2416001008/WC/10365683) GP 16/10/2022 277325.84 17674.97 266484 5000
83  TILEIBANI KENDEIJHORI STAGGERED CONTOUR TRENCH AT BENTKARBAHAL  (2416001009/WC/10432527) GP 29/04/2022 186301.67 13698.32 103293 0
84  TILEIBANI KENDEIJHORI LBCD AT BARGHATHODNATOPA (5NOS)  (2416001009/WC/10430552) GP 06/11/2022 223669.51 36957.15 187504 0
85  TILEIBANI KENDEIJHORI STAGGERED TRENCH AT GUNDEIMURA  (2416001009/WC/10497883) GP 06/11/2022 284459.44 18540.56 114810 0
86  TILEIBANI KENDEIJHORI STAGGERED TRENCH AT BARHAMUSA  (2416001009/WC/10497884) GP 06/11/2022 284459.44 18540.56 242520 0
87  TILEIBANI KENDEIJHORI STAGGERED TRENCH AT JAISENDHA  (2416001009/WC/10498376) GP 06/11/2022 284459.44 18540.56 166840 0
88  TILEIBANI KENDEIJHORI STAGGERED TRENCH AT MANIKANCHANPUR  (2416001009/WC/10498377) GP 25/08/2022 284459.44 18540.56 98040 0
89  TILEIBANI KENDEIJHORI STAGGERED TRENCH AT THELKOGUDI  (2416001009/WC/10498379) GP 06/11/2022 284459.44 18540.56 230265 0
90  TILEIBANI LAIMORA Imp. of Tranch Cum field Bounding at Tipirisingha  (2416001010/WC/10436759) GP 04/11/2022 180432.95 19567.05 183816 13241.6
91  TILEIBANI LAIMORA Imp.of Tranch Cum Field Bounding at-Bhaluguha  (2416001010/WC/10436760) GP 20/10/2022 180432.95 19567.05 166379 9120.8
92  TILEIBANI LAIMORA Imp. of Tranch Cum Field bounding at-Salohi  (2416001010/WC/10436762) GP 04/11/2022 180432.95 16944.25 173136 9120.8
93  TILEIBANI LAIMORA Imp. of Tranch Cum Field bounding at-Purunapani  (2416001010/WC/10436763) GP 20/10/2022 180432.95 16944.25 172992 9120.8
94  TILEIBANI LAIMORA TRENCH CUM FIELD BUNDING AT LAIMURA NUANALI  (2416001010/WC/10496458) GP 22/11/2022 196356.37 17643.63 184900 15530
95  TILEIBANI LAIMORA LBCD WORK AT BHALUGUHA LIMJHARAN NALLA  (2416001010/WC/10427839) GP 30/03/2023 223669.51 36957.15 180378 0
96  TILEIBANI LAIMORA LBCD WORK AT NAGDO NALLA  (2416001010/WC/10427846) GP 30/03/2023 209269.56 45892.6 112122 7060.4
97  TILEIBANI LAIMORA Imp. of Steggered/CounterTranch at - Kandarpa  (2416001010/WC/10436753) GP 30/03/2023 281051.52 18948.47 236148 0
98  TILEIBANI LAIMORA IMP.OF MUSAPOSI KATA  (2416001010/WC/10365596) GP 22/11/2022 268895.35 23105.48 240600 4056
99  TILEIBANI LAIMORA PANIBHANDAR UPPAR KATA  (2416001010/WC/10365661) GP 22/11/2022 277325.84 17674.97 197817 2028
100  TILEIBANI LAIMORA LBCD WORK AT PANIBHANDAR GHUGAR NALLA  (2416001010/WC/10427838) GP 22/11/2022 209269.56 45892.6 144072 11181.2
101  TILEIBANI LAIMORA LBCD WORK AT TIPIRISINGHA PANPOSH NALLA  (2416001010/WC/10427842) GP 04/11/2022 223669.51 36957.15 193542 11181.2
102  TILEIBANI LAIMORA LBCD WORK AT LAIMURA NALLA  (2416001010/WC/10427845) GP 04/11/2022 209269.56 45892.6 203274 8296.8
103  TILEIBANI LAIMORA Imp. of Steggered/Counter Tranch at tipirisingha  (2416001010/WC/10436752) GP 30/12/2022 281051.52 15922.32 243012 0
104  TILEIBANI LAIMORA Imp. of Steggered/Counter Tranch at -Purunapani  (2416001010/WC/10436757) GP 30/12/2022 281051.52 15922.32 272928 0
105  TILEIBANI LAIMORA Imp. of Steggered/Counter Tranch at-Salohi  (2416001010/WC/10436758) GP 31/10/2022 281051.52 15922.32 268418 13241.6
106  TILEIBANI LAIMORA STAGGERED TRENCH AT NAGDO  (2416001010/WC/10496455) GP 30/03/2023 284459.44 18540.56 224336 0
107  TILEIBANI LAIMORA STAGGERED TRENCH AT LAIMURA  (2416001010/WC/10496454) GP 22/11/2022 284459.44 18540.56 285337 11318
108  TILEIBANI PARPOSI TRENCH CUM FIELD BUNDING  (2416001011/WC/10436007) GP 04/08/2022 180432.95 16944.25 91290 11180
109  TILEIBANI PARPOSI TRENCH CUM FIELD BUINDING AT KERABAHAL  (2416001011/WC/10495638) GP 01/11/2022 196356.37 17643.63 186506 15830
110  TILEIBANI PARPOSI TRENCH CUM FIELD BUNDING AT CHILANTIKHOL  (2416001011/WC/10495646) GP 01/11/2022 196356.37 17643.63 186620 13724
111  TILEIBANI PARPOSI TRENCH CUM FIELD BUNDING AT PARPOSI  (2416001011/WC/10495647) GP 01/11/2022 196356.37 17643.63 193003 15780
112  TILEIBANI PARPOSI IMP.OF KASARLOI BANDHA  (2416001011/WC/10365688) GP 23/03/2023 277325.84 17674.97 132498 13004
113  TILEIBANI PARPOSI IMP.OF TELISUAN BANDHA  (2416001011/WC/10365689) GP 04/11/2022 277325.84 17674.97 108664 12788
114  TILEIBANI PARPOSI Staggered/contour trench  (2416001011/WC/10436160) GP 01/11/2022 281051.52 15922.32 184040 13624
115  TILEIBANI PARPOSI STAGGERED CONTOUR TRENCH AT TASARDA  (2416001011/WC/10495650) GP 01/11/2022 284459.44 18540.56 220590 13724
116  TILEIBANI PARPOSI STAGGERED CONTOUR TRENCH AT DURIJUNGLE  (2416001011/WC/10495660) GP 01/11/2022 284459.44 18540.56 113090 9512
117  TILEIBANI PARPOSI STAGGERED CONTOUR TRENCH AT KASARLAI  (2416001011/WC/10495662) GP 01/11/2022 284459.44 18540.56 240800 13624
118  TILEIBANI PARPOSI STAGGERED CONTOUR TRENCH AT KERABAHAL  (2416001011/WC/10495664) GP 01/11/2022 284459.44 18540.56 191882 15930
119  TILEIBANI PARPOSI STAGGERED CONTOUR TRENCH AT SAMASINGHA  (2416001011/WC/10495667) GP 01/11/2022 284459.44 18540.56 165980 13688
120  TILEIBANI SADO STAGGERED TRENCH AT-KALCHIPODADIHI  (2416001012/WC/10430583) GP 11/11/2022 186301.67 13698.32 178020 12680
121  TILEIBANI SADO STAGGERED TRENCH AT-KHAMARBAHAL  (2416001012/WC/10430586) GP 11/11/2022 186301.67 13698.32 184255 12680
122  TILEIBANI SADO LBCD AT KALCHIPODADIHI BHUGURA NALLA  (2416001012/WC/10497840) GP 11/11/2022 137447.87 35042.72 135020 58444
123  TILEIBANI SADO LBCD AT GAMBHARIBHUIN NALLA  (2416001012/WC/10498136) GP 11/11/2022 137447.87 35042.72 135880 58443
124  TILEIBANI SADO LBCD AT TURANG CHEMNA NALLA  (2416001012/WC/10429596) GP 10/09/2022 223669.51 36957.15 191780 63375
125  TILEIBANI SADO LBCD AT GURULIA NALLA  (2416001012/WC/10429605) GP 11/11/2022 223669.51 36957.15 221665 67203
126  TILEIBANI SUGUDA TRENCH CUM FIELD BUNDING at Gunduriposi  (2416001013/WC/10438918) GP 10/11/2022 180389.14 14940.28 173052 13112
127  TILEIBANI SUGUDA LBCD AT KANKANIA NALLAH  (2416001013/WC/10442971) GP 09/03/2023 135664.17 35737.21 142053 34348
128  TILEIBANI SUGUDA Trench cum Field Bunding at SugudaDandabandha  (2416001013/WC/10495588) GP 01/08/2022 196356.37 17643.63 202100 0
129  TILEIBANI SUGUDA Trench cum field Bunding at Gunduriposi colony 2nd phase  (2416001013/WC/10495624) GP 09/03/2023 196356.37 17643.63 186924 9000
130  TILEIBANI SUGUDA STAGGERED CUM CONTOUR TRENCH at Khuntiapali  (2416001013/WC/10437752) GP 30/06/2022 275841.95 20158.05 247158 4056
131  TILEIBANI SUGUDA STAGGERED CONTOUR STRENCH AT SUGUDA  (2416001013/WC/10443988) GP 09/08/2022 279227.93 17932.21 280542 17436
132  TILEIBANI SUGUDA CROSS BOND AT SUGUDA  (2416001013/WC/10473886) GP 03/08/2022 215294.55 83459.48 218400 0
133  TILEIBANI SUGUDA Staggered Trench at Gunduriposi colony Play ground  (2416001013/WC/10495591) GP 25/05/2022 284459.44 18540.56 194360 0
134  TILEIBANI SUGUDA Staggered Trench at Suguda makarkani  (2416001013/WC/10495610) GP 09/08/2022 284459.44 18540.56 292400 5000
135  TILEIBANI SUGUDA Staggered trench at Gunduriposi colony huli 2nd phase  (2416001013/WC/10495618) GP 09/03/2023 284459.44 18540.56 262085 13112
136  TILEIBANI SUGUDA Staggered trench at Suguda Kathahuli  (2416001013/WC/10495622) GP 09/08/2022 284459.44 18540.56 290250 5000
137  TILEIBANI SUGUDA Imp of Khuntiapali Kata  (2416001013/WC/10453227) GP 02/08/2022 474991.28 23190.32 462714 2000
138  TILEIBANI TAINSAR LBCD WORK AT SUKUNALI TAINSAR  (2416001014/WC/10439736) GP 22/08/2022 62780.87 24637.93 84174 0
139  TILEIBANI TAINSAR LBCD WORK AT MUSABIRA NALLA  (2416001014/WC/10439738) GP 22/08/2022 62780.87 24637.93 83214 0
140  TILEIBANI TAINSAR LBCD WORK AT JHALIAMARA  (2416001014/WC/10439290) GP 31/10/2022 62780.87 24637.93 96216 0
141  TILEIBANI TAINSAR LBCD WORK AT BHUKABEDA  (2416001014/WC/10439292) GP 22/08/2022 62780.87 21614.18 41850 0
142  TILEIBANI TAINSAR LBCD WORK AT MASINTA  (2416001014/WC/10441547) GP 31/10/2022 62780.87 21714.79 95013 0
143  TILEIBANI TAINSAR LBCD WORK AT BANDHAKHOL  (2416001014/WC/10441548) GP 14/11/2022 62780.87 21714.79 95013 0
144  TILEIBANI TAINSAR LBCD WORK AT HATITUPA NALI  (2416001014/WC/10496040) GP 28/10/2022 63477.5 21807.42 86430 0
145  TILEIBANI TAINSAR LBCD WORK AT KATEI  (2416001014/WC/10450892) GP 14/11/2022 62780.87 21800.5 54180 0
146  TILEIBANI TAINSAR LBCD AT KATEI  (2416001014/WC/10496053) GP 01/11/2022 207870.8 46578.52 125006 63921
147  TILEIBANI TAINSAR IMPROVEMENT OF KATEI KATA  (2416001014/WC/10394469) GP 22/08/2022 272783.11 15938.13 275928 0
148  TILEIBANI TAINSAR LBCD AT BANDHAKHOL  (2416001014/WC/10496042) GP 14/11/2022 207870.8 46578.52 101910 0
149  TILEIBANI TAINSAR STAGGERED TRENCH AT MASINTA  (2416001014/WC/10496048) GP 01/11/2022 284459.44 18540.56 262932 13388
150  TILEIBANI TAINSAR STAGGERED TRENCH AT KATEI  (2416001014/WC/10496044) GP 01/11/2022 284459.44 18540.56 151236 13388
151  TILEIBANI TAINSAR STAGGERED TRENCH AT BANDHAKHOL  (2416001014/WC/10496051) GP 01/11/2022 284459.44 10116.56 269424 9212
152  TILEIBANI TAINSAR STAGGERED TRENCH AT SUKAPADAN  (2416001014/WC/10501732) GP 28/10/2022 284459.44 18540.56 243948 0
153  TILEIBANI TALKUNDI IMPROVEMENT OF JALAPAL KATA  (2416001015/WC/10475268) GP 04/11/2022 320988.17 165042.56 179310 5000
154  TILEIBANI TILEIBANI Countour Trench Cum Bund At Tilrisarua  (2416001016/WC/10436356) GP 25/12/2022 278520.83 15897.8 278022 19168
155  TILEIBANI TILEIBANI LBCD of Gudbanga nala Bileighati  (2416001016/WC/10436363) GP 02/12/2022 223669.51 36957.15 212742 29336
156  TILEIBANI TILEIBANI LBCD AT PRAVASUNI KUCHKUCHA NALA  (2416001016/WC/10495702) GP 02/12/2022 208708.89 47491.06 244670 50201
157  TILEIBANI TILEIBANI LBCD AT ASURKHUL NALA  (2416001016/WC/10495715) GP 02/12/2022 208708.89 47491.06 218232 50201
158  TILEIBANI TILEIBANI LBCD AT SUKHAKANI NALA  (2416001016/WC/10495721) GP 02/12/2022 208708.89 47491.06 211130 54257
159  TILEIBANI TILEIBANI STAGGEERED TRENCH AT ASURKHUL   (2416001016/WC/10496342) GP 02/12/2022 284459.44 18540.56 286740 23354
160  TILEIBANI TILEIBANI STAGGERED TRENCH AT BARAGADIA  (2416001016/WC/10495732) GP 02/12/2022 284459.44 18540.56 171570 17270
161  TILEIBANI TILEIBANI IMP of Munda sahi Bandha and Guardwall  (2416001016/WC/10476252) GP 02/11/2022 437573.46 57665.78 287455 0
162  TILEIBANI PALAKUDAR TRENCH CUM FIELD BUNDING  (2416001017/WC/10436859) GP 04/11/2022 182405.18 14938.6 170925 18112
163  TILEIBANI PALAKUDAR TRENCH CUM FIELD BUNDING  (2416001017/WC/10436858) GP 04/11/2022 182405.18 14938.6 176300 13112
164  TILEIBANI PALAKUDAR STAGGERED CONTOUR TRENCH AT UCHHABAPALI  (2416001017/WC/10436505) GP 02/11/2022 281051.52 7810.32 229872 11144
165  TILEIBANI PALAKUDAR STAGGERED CONTOUR TRENCH AT KUNJABAHAL  (2416001017/WC/10436506) GP 02/11/2022 282740.19 7826.8 219618 13112
166  TILEIBANI PALAKUDAR STAGGERED CONTOUR TRENCH AT DHAURAKHAMAN  (2416001017/WC/10436503) GP 28/04/2022 281051.52 7810.32 212850 5000
167  TILEIBANI KALANDA LBCD AT BASUDEVPUR  (2416001018/WC/10495762) GP 21/03/2023 137447.87 34042.72 129426 60549.46
168  TILEIBANI KALANDA LBCD AT JHATKIPOSI BALANDA  (2416001018/WC/10495360) GP 29/10/2022 137447.87 34042.72 135450 56214
169  TILEIBANI KALANDA LBCD AT SAMANTARAPALI  (2416001018/WC/10495374) GP 29/10/2022 137447.87 34042.72 138030 58320
170  TILEIBANI KALANDA LBCD AT BALANDA  (2416001018/WC/10495754) GP 29/10/2022 137447.87 34042.72 134160 5000
171  TILEIBANI KALANDA TRENCH CUM FIELD BUNDING AT BALANDA  (2416001018/WC/10495758) GP 21/03/2023 196356.37 17643.63 182262 17341.69
172  TILEIBANI KALANDA TRENCH CUM FIELD BUNDING AT PATHARUSAHI BALANDA  (2416001018/WC/10495759) GP 31/03/2023 196356.37 17643.63 194490 9212
173  TILEIBANI KALANDA TRENCH CUM FIELD BUNDING AT CHADAKMARA  (2416001018/WC/10495788) GP 30/12/2022 196356.37 17643.63 195400 15424
174  TILEIBANI KALANDA TRENCH CUM FIELD BUNDING AT KALANDA  (2416001018/WC/10496001) GP 22/12/2022 196356.37 17643.63 189076 15424
175  TILEIBANI KALANDA TRENCH CUM FIELD BUNDING AT KHUNTAPASI KALANDA  (2416001018/WC/10496002) GP 21/03/2023 196356.37 17643.63 179376 17341.69
176  TILEIBANI KALANDA TRENCH CUM FIELD BUNDING AT NUAGAON  (2416001018/WC/10496003) GP 29/10/2022 196356.37 17643.63 170280 15424
177  TILEIBANI KALANDA TRENCH CUM FIELD BUNDING AT JHATIKIPASI BALANDA  (2416001018/WC/10496815) GP 13/11/2022 198071.16 16428.84 197100 9212
178  TILEIBANI KALANDA TRENCH CUM FIELD BUNDING AT SAMANTARAPALI  (2416001018/WC/10498555) GP 28/11/2022 196356.37 17643.63 195924 15424
179  TILEIBANI KALANDA DIGGING NEW POND AT CHADAKMARA  (2416001018/WC/10413912) GP 31/05/2022 278686.04 17313.97 285444 11084
180  TILEIBANI KALANDA STAGGERED/CONTOUR TRENCH AT KALANDA  (2416001018/WC/10495793) GP 04/03/2023 284459.44 17540.56 278832 16424
181  TILEIBANI KALANDA STAGGERED CONTOUR TRENCH AT BALANDA  (2416001018/WC/10495368) GP 29/10/2022 286174.38 16825.62 244058 17636
182  TILEIBANI KALANDA STAGGERED/CONTOUR TRENCH AT BASUDEVPUR  (2416001018/WC/10495764) GP 01/11/2022 282744.5 18255.5 280982 13424
183  TILEIBANI KALANDA STAGGERED/CONTOUR TRENCH AT KHUNTAPASI KALANDA  (2416001018/WC/10495999) GP 22/12/2022 286174.38 16825.62 271716 15424
184  TILEIBANI KALANDA STAGGERED/CONTOUR TRENCH AT SAMANTARAPALI  (2416001018/WC/10496804) GP 22/12/2022 284459.44 18540.56 277116 11212
185  TILEIBANI JHARMUNDA LBCD AT BAUNSNALI  (2416001019/WC/10495537) GP 31/10/2022 137447.87 35042.72 122120 13424
186  TILEIBANI JHARMUNDA LBCD AT DANEIDIHI  (2416001019/WC/10495573) GP 31/10/2022 137447.87 35042.72 96750 13424
187  TILEIBANI JHARMUNDA CCT CUM FIELD BUNDING AT KADALIMUNDA  (2416001019/WC/10495540) GP 04/11/2022 196356.37 17643.63 188340 15680
188  TILEIBANI JHARMUNDA CCT AT KADALIMUNDA  (2416001019/WC/10495546) GP 18/01/2023 196356.37 17643.63 122550 0
189  TILEIBANI JHARMUNDA CCT CUM FIELD BUNDING AT KADODIHI  (2416001019/WC/10495617) GP 18/01/2023 196356.37 17643.63 182280 0
190  TILEIBANI JHARMUNDA CCT CUM FIELD BUNDING DHENGHURJORE  (2416001019/WC/10495621) GP 04/11/2022 196356.37 17643.63 177375 13262
191  TILEIBANI JHARMUNDA CCT CUM FIELD BUNDING AT JHARMUNDA  (2416001019/WC/10495676) GP 31/10/2022 196356.37 17643.63 196940 11468
192  TILEIBANI JHARMUNDA IMP.OF KADODIHI BANDHA  (2416001019/WC/10365693) GP 04/11/2022 277325.84 17674.97 129756 5000
193  TILEIBANI JHARMUNDA LBCD WORK AT KHAKONALI NALLA  (2416001019/WC/10436173) GP 06/12/2022 209269.56 37780.6 122517 7457
194  TILEIBANI JHARMUNDA STAGGERED/CONTOUR TRENCH AT BAUNSANALI  (2416001019/WC/10436490) GP 04/11/2022 281051.52 18948.47 175527 11174
195  TILEIBANI JHARMUNDA STAGGERED CONTOUR TRENCH AT KHARIANALI  (2416001019/WC/10436834) GP 04/11/2022 281051.52 15922.32 187146 15290
196  TILEIBANI JHARMUNDA IMP. OF JUNAPANI KATA, KADALIMUNDA  (2416001019/WC/10479258) GP 31/10/2022 264553.94 33446.06 263934 11288
197  TILEIBANI GANDAM TRENCH CUM FIELD BUNDING AT GANGAJAL  (2416001020/WC/10436379) GP 18/04/2022 174922.8 20051.6 176730 0
198  TILEIBANI GANDAM TRENCH CUM FIELD BUNDING AT TELIKUSAM  (2416001020/WC/10436381) GP 18/04/2022 174922.8 20051.6 172833 0
199  TILEIBANI GANDAM IMP.OF KHOLDIHI BANDHA  (2416001020/WC/10365691) GP 31/12/2022 278018.16 16982.88 207676 0
200  TILEIBANI GANDAM BHALUCHUAN STAGGERED TRENCH  (2416001020/WC/10495184) GP 10/10/2022 284459.44 18540.56 183180 0
201  TILEIBANI GANDAM STAGGERED TRENCH JOGIBENUA  (2416001020/WC/10495192) GP 10/10/2022 284459.44 18540.56 242406 0
202  TILEIBANI GANDAM GANDAM STAGGERED TRENCH  (2416001020/WC/10495186) GP 15/05/2022 284459.44 18540.56 239940 0
203  TILEIBANI GANDAM KHOLDIHI STAGGERED TRENCH  (2416001020/WC/10495188) GP 15/05/2022 284459.44 18540.56 287756 0
204  BARKOTE BASALOI Trench cum field Bunding at Basaloi  (2416002004/WC/10435744) GP 05/08/2022 172298.96 22863.36 171396 0
205  BARKOTE BASALOI Trench cum field Bunding at Gariaposhi  (2416002004/WC/10435743) GP 23/08/2022 172298.96 22863.36 193752 0
206  BARKOTE BASALOI Trench-Cum-Field Bunding at Gariapasi   (2416002004/WC/10500420) GP 19/06/2022 181683.6 16316.8 180815 5000
207  BARKOTE BASALOI LBCD of Asurkhol Nalha at Kalkatha  (2416002004/WC/10430697) GP 16/08/2022 209269.56 45892.6 165186 0
208  BARKOTE BASALOI LBCD of Pita Nalha at Kalkatha  (2416002004/WC/10430698) GP 23/08/2022 209269.56 45892.6 168912 0
209  BARKOTE BASALOI IMP OF BAIKUNTHA KATA, KALKATH  (2416002004/WC/10365782) GP 05/08/2022 456712.35 34167.12 449400 0
210  BARKOTE BIJAYANAGAR Trench Cum field Bunding at Bijayanagar  (2416002005/WC/10435746) GP 02/09/2022 172298.96 22863.36 173880 13112
211  BARKOTE BIJAYANAGAR Trench-Cum-Field Bunding at Kaunsibahal  (2416002005/WC/10500442) GP 02/09/2022 181683.6 16816.8 177160 5000
212  BARKOTE BIJAYANAGAR LBCD of Bijaynagar Nalha  (2416002005/WC/10430285) GP 08/08/2022 209269.56 45892.6 91908 11056
213  BARKOTE BIJAYANAGAR LBCD of Dhaba Pakha Nalha of Kaunsibahal  (2416002005/WC/10430294) GP 20/10/2022 209269.56 45892.6 94392 9056
214  BARKOTE BIJAYANAGAR Imp. of Amuruta jena Ghara Pakha Canal Check Dam,Bijayanagar  (2416002005/WC/1380060) GP 20/10/2022 50000 650000 65472 616934.7267
215  BARKOTE DANRA Trench-Cum-Field Bunding at Chakrapali  (2416002007/WC/10500468) GP 18/06/2022 172599.42 25361.96 180600 0
216  BARKOTE DANRA Trench-Cum-Field Bunding at Sirapali  (2416002007/WC/10500480) GP 07/11/2022 172599.42 25361.96 184010 9260
217  BARKOTE DANRA Trench cum field Bunding at Balita  (2416002007/WC/10435735) GP 18/06/2022 174922.8 21889.6 178848 4056
218  BARKOTE DANRA Trench cum field Bunding at Sirapali  (2416002007/WC/10435737) GP 07/11/2022 174922.8 20077.2 174708 9056
219  BARKOTE DANRA Trench-Cum-Field Bunding at Balita  (2416002007/WC/10500466) GP 18/06/2022 172599.42 25361.96 178880 0
220  BARKOTE DANRA LBCD of Ambakhola Nalha  (2416002007/WC/10430349) GP 18/06/2022 209269.56 46892.6 111780 11084
221  BARKOTE DANRA LBCD of Chakrapali jharjhari Nalha  (2416002007/WC/10430355) GP 18/06/2022 209269.56 46892.6 107640 15140
222  BARKOTE DANRA LBCD of Chakadihi Hardakhol Nalha  (2416002007/WC/10430358) GP 08/08/2022 209269.56 46892.6 108054 2028
223  BARKOTE DANTARIBAHAL Trench-Cum-Field Bunding at Kusumkata  (2416002008/WC/10500489) GP 19/06/2022 172599.42 25361.96 169420 8352
224  BARKOTE GURSANG LBCd of Kanjia Nalha of Baidharnagar  (2416002009/WC/10500544) GP 02/11/2022 66025.68 19660.61 75895 5000
225  BARKOTE GURSANG LBCD of Mohannali Nalha  (2416002009/WC/10500846) GP 20/01/2023 66025.68 19660.61 51600 5000
226  BARKOTE GURSANG Cross band at jautukanala 4nos gurusang  (2416002009/WC/1363263) GP 20/08/2022 180000 20000 116616 0
227  BARKOTE GURSANG Trench Cum field Bunding at Gursang  (2416002009/WC/10435756) GP 02/11/2022 174922.8 20077.2 167050 5000
228  BARKOTE GURSANG Trench-Cum-Field Bunding at Mandasila-B  (2416002009/WC/10500538) GP 02/11/2022 172599.42 25361.96 170280 5000
229  BARKOTE GURSANG Trench Cum Field Bunding at Remala Sahi of Baidharnagar  (2416002009/WC/10505881) GP 02/11/2022 172599.42 25361.96 181030 5000
230  BARKOTE GURSANG Trench Cum Field Bunding at Sindur Munda of Baidharnagar  (2416002009/WC/10505884) GP 02/11/2022 172599.42 25361.96 145770 5000
231  BARKOTE GURSANG Trench-Cum-Field Bunding at Play Ground Side of Depatala  (2416002009/WC/10507924) GP 02/11/2022 172599.42 25361.96 175440 5000
232  BARKOTE GURSANG Imp. of Ratab Bileisali Kata & Cenal,Ratab  (2416002009/WC/1379044) GP 04/11/2022 180000 120000 283888 3960
233  BARKOTE GURSANG LBCD of Jharana Nalha  (2416002009/WC/10430378) GP 02/11/2022 209269.56 46892.6 116334 5000
234  BARKOTE GURSANG LBCD of Purunapani Nalha  (2416002009/WC/10430379) GP 17/12/2022 209269.56 47227.96 120888 5000
235  BARKOTE JHARAKANDHAL Trench Cum field Bunding at Thakurpali  (2416002010/WC/10435757) GP 25/09/2022 166176.66 28886.12 121716 0
236  BARKOTE JHARAKANDHAL Trench Cum field Bunding at Gurjang  (2416002010/WC/10435758) GP 03/11/2022 166176.66 28886.12 170568 0
237  BARKOTE JHARAKANDHAL Staggered Trench at Jharakandhal  (2416002010/WC/10500412) GP 03/11/2022 252631.05 41798.26 262730 0
238  BARKOTE JHARAKANDHAL Staggered Trench at Khulundikudar  (2416002010/WC/10500413) GP 03/11/2022 252631.05 41798.26 260150 5000
239  BARKOTE JHARAKANDHAL Staggered Trench at Thakurpali  (2416002010/WC/10500416) GP 01/11/2022 252631.05 41798.26 268320 5000
240  BARKOTE KADUPADA Staggered Trench at Bramhandei  (2416002011/WC/10500423) GP 16/10/2022 252631.05 41798.26 251100 11264
241  BARKOTE KADUPADA Staggered Trench at Masinta  (2416002011/WC/10500435) GP 17/11/2022 252631.05 41798.26 252610 11264
242  BARKOTE KADUPADA Staggered Trench at Singuri  (2416002011/WC/10500441) GP 16/10/2022 252631.05 41798.26 251120 11264
243  BARKOTE KADUPADA Staggered Trench at Singuri  (2416002011/WC/10501827) GP 16/10/2022 252631.05 41798.26 252410 11264
244  BARKOTE KALIAPAL Trench-Cum-Field Bunding at Kaliapal  (2416002012/WC/10500547) GP 01/11/2022 172599.42 25361.96 167000 15352
245  BARKOTE KALIAPAL Trench-Cum-Field Bunding at Kaliapal  (2416002012/WC/10500550) GP 01/11/2022 172599.42 25361.96 167700 15352
246  BARKOTE KALIAPAL Trench-Cum-Field Bunding at Lalaposhi  (2416002012/WC/10500552) GP 01/11/2022 172599.42 25361.96 166840 17440
247  BARKOTE KALIAPAL Trench-Cum-Field Bunding at Nuakesala  (2416002012/WC/10500553) GP 01/11/2022 172599.42 25361.96 171355 15352
248  BARKOTE KALIAPAL Trench-Cum-Field Bunding at Talabahali  (2416002012/WC/10500555) GP 01/11/2022 172599.42 25361.96 171355 17440
249  BARKOTE KALLA Trench Cum Field Bunding of Markandpur  (2416002013/WC/10455610) GP 02/11/2022 163990.13 16104.25 96048 15352
250  BARKOTE KALLA Trench cum Field Bunding of Kalla Kaman Huli  (2416002013/WC/10455611) GP 02/11/2022 163990.13 16104.25 106605 15352
251  BARKOTE KALLA Trench cum field Bunding at Kisan Gayalmara  (2416002013/WC/10435732) GP 25/11/2022 174922.8 20077.2 159390 14732
252  BARKOTE KALLA Staggered Trench at Canal Side Huli  (2416002013/WC/10500446) GP 02/11/2022 252631.05 41798.26 233275 26616
253  BARKOTE KALLA Staggered Trench at Kulha Sahi Huli  (2416002013/WC/10500453) GP 02/11/2022 252631.05 41798.26 239940 26616
254  BARKOTE KALLA Staggered Trench at Play Ground Side Huli  (2416002013/WC/10500473) GP 02/11/2022 252631.05 41798.26 242520 26616
255  BARKOTE KALLA Staggered Trench at Bandha Side  (2416002013/WC/10500478) GP 02/11/2022 252631.05 41798.26 249400 26616
256  BARKOTE KALLA Staggered Trench at Markandapur Back Side Huli  (2416002013/WC/10500482) GP 02/11/2022 252631.05 41798.26 247250 24528
257  BARKOTE KALLA Staggered Trench at Jhilipi Huli  (2416002013/WC/10500488) GP 02/11/2022 252631.05 41798.26 248110 26616
258  BARKOTE KALLA Imp. of Kalla Bad Bandha Guardwall  (2416002013/WC/1358518) GP 25/03/2023 200000 300000 136068 230605.57
259  BARKOTE KANDHAL IMp. of Baghamunda Upar Katta,Baghamunda  (2416002014/WC/1364563) GP 02/06/2022 300000 100000 362112 2040
260  BARKOTE KANTAPALI Trench cum field Bunding at Dayankhot  (2416002015/WC/10435728) GP 30/10/2022 166176.66 28886.12 139254 5000
261  BARKOTE KANTAPALI LBCD of Regada Kamala Jharan Nalha  (2416002015/WC/10430343) GP 30/10/2022 209269.56 45892.6 94392 13112
262  BARKOTE KANTAPALI LBCD of Dangapal Baluanath Jharan Nalha  (2416002015/WC/10430341) GP 10/05/2022 209269.56 45892.6 153594 51760
263  BARKOTE KANTAPALI Staggered Trench at Baishnabpali  (2416002015/WC/10500512) GP 30/10/2022 252631.05 41798.26 249830 5000
264  BARKOTE KANTAPALI Staggered Trench at Gobindapali  (2416002015/WC/10500516) GP 30/10/2022 252631.05 41798.26 247680 5000
265  BARKOTE KANTAPALI Staggered Trench at Gundeimara  (2416002015/WC/10500520) GP 30/10/2022 252631.05 41798.26 248540 5000
266  BARKOTE KANTAPALI Staggered Trench at Makarmunda  (2416002015/WC/10500523) GP 30/10/2022 252631.05 41798.26 251550 5000
267  BARKOTE KANTAPALI Imp. of Dangapal Uppar Kata,Dangapal  (2416002015/WC/10343315) GP 21/08/2022 450000 50000 115056 35686
268  BARKOTE KANTAPALI Reno of Existing Check Dam over Maa Jhia Nallha of Kanjiam  (2416002015/WC/10478605) GP 30/10/2022 296361.14 474433.74 292554 427584.4221
269  BARKOTE KAUNSIBAHAL Trench Cum field Bunding at Majhichakundapal  (2416002016/WC/10435760) GP 29/10/2022 174922.8 20077.2 170154 9056
270  BARKOTE KAUNSIBAHAL Trench-Cum-Field Bunding at Nanei Sahi  (2416002016/WC/10500646) GP 29/10/2022 172599.42 25361.96 172215 11264
271  BARKOTE KELDA LBCD of Sana Nalha  (2416002017/WC/10501103) GP 23/03/2023 66025.68 19660.61 64500 16780.62
272  BARKOTE KELDA 5 Nos of LBCD of Khuntabahal Nala  (2416002017/WC/10430019) GP 23/03/2023 104634.78 24396.54 104633 23004.24
273  BARKOTE KELDA 6 nos of LBCD of Bakulimunda Nala  (2416002017/WC/10429988) GP 23/03/2023 125561.74 27952.36 97977 26279.2
274  BARKOTE KELDA Trench-Cum-Field Bunding at Rabanbasa  (2416002017/WC/10500657) GP 23/03/2023 172599.42 25361.96 150178 20636
275  BARKOTE KELDA 4 Nos of LBCD of Gudabhanga Nala  (2416002017/WC/10430021) GP 23/03/2023 209269.56 45892.6 120591 42108.48
276  BARKOTE KELDA Imp of Kardadarha mati kenal khanana  (2416002017/WC/10444615) GP 07/06/2022 442554.68 40650.49 422374 41344
277  BARKOTE MADHYAPUR Trench-Cum-Field Bunding at Ragunathapur  (2416002018/WC/10500661) GP 10/08/2022 154521.9 35817.19 170280 9176
278  BARKOTE MADHYAPUR Trench-Cum-Field Bunding at Laxmipur  (2416002018/WC/10500670) GP 10/08/2022 154521.9 35817.19 175440 13520
279  BARKOTE MADHYAPUR Trench-Cum-Field Bunding at Landijhari  (2416002018/WC/10500673) GP 10/08/2022 154521.9 35817.19 188340 9176
280  BARKOTE MADHYAPUR Staggered Trench at Goyalmora  (2416002018/WC/10500845) GP 17/08/2022 246499.22 38736.94 277530 11390
281  BARKOTE MADHYAPUR Staggered Trench at Basantapur  (2416002018/WC/10500859) GP 10/08/2022 246499.22 38736.94 275474 19910
282  BARKOTE RAITABAHAL Trench cum Field Bunding at Siripur  (2416002019/WC/10580794) GP 03/11/2022 181970.45 16603.33 148518 0
283  BARKOTE RAMBHEI Trench cum field Bunding at Tileimal  (2416002020/WC/10435722) GP 24/06/2022 172298.96 22863.36 121716 13112
284  BARKOTE RAMBHEI Trench cum field Bunding at Harekrushnapur  (2416002020/WC/10435723) GP 11/08/2022 172298.96 22863.36 180170 5000
285  BARKOTE RAMBHEI Trench-Cum-Field Bunding at Mahajanmunda  (2416002020/WC/10500701) GP 11/08/2022 177141.51 21123.38 178020 5000
286  BARKOTE SARUALI Trench-Cum-Field Bunding at Outal  (2416002021/WC/10500732) GP 30/08/2022 165559.18 26315.56 153080 0
287  BARKOTE SARUALI Trench-Cum-Field Bunding at Khuntadihi  (2416002021/WC/10500744) GP 30/08/2022 165559.18 26315.56 166840 0
288  BARKOTE SARUALI Construction of Checkdam at Outal  (2416002021/WC/10425982) GP 16/08/2022 221824.26 558967.41 77418 576218.0159
289  BARKOTE SINGSAL Trench-Cum-Field Bunding at Lekhapali  (2416002022/WC/10500777) GP 14/11/2022 172599.42 25361.96 168560 15352
290  BARKOTE SINGSAL Trench-Cum-Field Bunding at Meghaparsanpur  (2416002022/WC/10500779) GP 14/11/2022 172599.42 25361.96 169850 17440
291  BARKOTE SINGSAL Trench-Cum-Field Bunding at Harekrushnapur  (2416002022/WC/10500786) GP 14/11/2022 172599.42 25361.96 172215 17440
292  BARKOTE SINGSAL IMP. OF PURUSOTTAMPUR BANDHA, JAGANNATHPUR  (2416002022/WC/10365303) GP 12/06/2022 256173.88 32825.74 182736 23064
293  BARKOTE SAIDA Trench Cum field Bunding at Saida  (2416002023/WC/10435723) GP 25/08/2022 170328.38 19127.25 167915 12260
294  BARKOTE SAIDA Trench cum field Bundding at Bhulumunda Tulabha Huli  (2416002023/WC/10506529) GP 25/08/2022 172599.42 25361.96 159099.55 14390
295  BARKOTE GOLABANDHA Trench Cum field Bunding at Dehurymunda  (2416002024/WC/10435715) GP 27/09/2022 163990.13 16104.25 161160 20112
296  BARKOTE GOLABANDHA Trench-Cum-Field Bunding at Thianal  (2416002024/WC/10500500) GP 19/10/2022 172599.42 25361.96 172378 18352
297  REAMAL ADAS Const of LBCD at Nisturduma Nalla  (2416003001/WC/10491815) GP 28/03/2023 57887.72 28387.37 55500 37509
298  REAMAL ADAS Const of LBCD at Andharikhol Nalla  (2416003001/WC/10491818) GP 03/11/2022 57887.72 28387.1 56760 4212
299  REAMAL ADAS Const of Gabion Structure on Dehurysahi Nalla(5nos.)  (2416003001/WC/10428178) GP 05/09/2022 46735.48 93388.84 44712 29868
300  REAMAL ADAS Const.of Gabion Structure on Andhari Nalla(5nos)  (2416003001/WC/10428291) GP 10/08/2022 46735.48 93388.84 87720 60546
301  REAMAL ADAS Const of Staggered trench at Anlakuli  (2416003001/WC/10490308) GP 10/08/2022 227900.17 16100.02 228115 13424
302  REAMAL ADAS Const of Staggered Trench at Bailodihi  (2416003001/WC/10490309) GP 10/08/2022 227900.17 16100.02 225965 15530
303  REAMAL ADAS Const.of Staggered Trench at Ratakhandi  (2416003001/WC/10490313) GP 10/08/2022 227900.17 16100.02 225965 15530
304  REAMAL ADAS Const of Staggered trench at Andharikhol  (2416003001/WC/10490316) GP 10/08/2022 227900.17 15703.02 225965 15530
305  REAMAL ADAS Const of Staggered Trench at Khairandha  (2416003001/WC/10490318) GP 10/08/2022 227900.17 15703.02 225965 15530
306  REAMAL ADAS Const of Staggered Trench at Butapali  (2416003001/WC/10490320) GP 10/08/2022 227900.17 15703.02 223385 15530
307  REAMAL ADAS Const of Staggered Trench at Pudapada  (2416003001/WC/10490322) GP 10/08/2022 227900.17 15703.02 226395 15530
308  REAMAL ADAS Const of Staggered Trench at Bhaliadihi  (2416003001/WC/10490325) GP 10/08/2022 227701.67 15701.05 227040 14477
309  REAMAL ADAS Const of Staggered Trench at Hilang Projecti  (2416003001/WC/10490328) GP 10/08/2022 227588.77 15699.91 223815 17636
310  REAMAL ADAS Const of Staggered Trench at Thelkobudi  (2416003001/WC/10490330) GP 10/08/2022 227900.17 15703.02 225965 15530
311  REAMAL ADAS Beautification of Rampali Village Bandha  (2416003001/WC/10411699) GP 14/05/2022 133575.64 324194.3 141066 347594.8062
312  REAMAL ADAS Beautification of Pond at Adas Bandh  (2416003001/WC/10457706) GP 05/09/2022 164936.84 303227.21 123840 312412.987
313  REAMAL ADAS Const of Check Dam and Canalling System at Banarpal Nalla  (2416003001/WC/10430670) GP 31/03/2023 214949.47 642946.08 214008 670907.8374
314  REAMAL ADAS Model Tank at Nabadiha Mahabandha  (2416003001/WC/10474158) GP 28/03/2023 226159.11 638107.07 224664 455320.5863
315  REAMAL BAGHBAR Const. of Gabion Structure at Kathiamunda  (2416003002/WC/10494484) GP 04/08/2022 18820.94 37077.31 18060 37746.8
316  REAMAL BAGHBAR Const. of Gabion Structure at Shikabera  (2416003002/WC/10494485) GP 04/08/2022 18820.94 37077.31 18060 37746.8
317  REAMAL BAGHBAR 2Nos Const of Gabion Structure on Khairanali Nalla  (2416003002/WC/10427910) GP 29/07/2022 18120.62 37928.76 18060 39644.94
318  REAMAL BAGHBAR 2Nos Const of Gabion Structure on Dimirikata Nalla  (2416003002/WC/10427911) GP 29/07/2022 18120.62 37928.76 18060 39644.94
319  REAMAL BAGHBAR Const. of Gabion Structure at Bali Kiari  (2416003002/WC/10494481) GP 29/07/2022 18820.94 37077.31 18060 37746
320  REAMAL BAGHBAR Const. of Gabion Structure at Milu Khol  (2416003002/WC/10494483) GP 29/07/2022 18820.94 37077.31 18060 37746
321  REAMAL BAGHBAR LBCD on Adipathar Nalla  (2416003002/WC/10436912) GP 03/11/2022 55733.76 25367.15 57620 30906
322  REAMAL BAGHBAR Const of LBCD on Andharikhol Nalla  (2416003002/WC/10436914) GP 29/07/2022 55733.76 26049.77 76176 16582
323  REAMAL BAGHBAR Const of LBCD on Dimilikata Nalla  (2416003002/WC/10436915) GP 03/11/2022 55733.76 26049.77 38502 19612
324  REAMAL BAGHBAR Const. of LBCD Matigadia Nalla  (2416003002/WC/10494468) GP 03/11/2022 57887.72 23387.1 52030 31660
325  REAMAL BAGHBAR Const. of LBCD Mohana Khali Nalla  (2416003002/WC/10494469) GP 29/03/2023 57887.72 23387.1 54168 33081.24
326  REAMAL BAGHBAR Const. of LBCD at Chua Nali Nalla  (2416003002/WC/10494471) GP 29/07/2022 57887.72 23387.1 58050 33766
327  REAMAL BAGHBAR Const. of LBCD at Mugarbania Nalla  (2416003002/WC/10494472) GP 29/07/2022 57887.72 23387.1 67295 33766
328  REAMAL BAGHBAR Const. of LBCD at Andharikhol Nalla  (2416003002/WC/10494473) GP 29/07/2022 57887.72 23387.1 58695 31660
329  REAMAL BAGHBAR Const. of LBCD at Pathargada Nalla  (2416003002/WC/10494477) GP 29/07/2022 57887.72 23387.1 53320 31660
330  REAMAL BAGHBAR Const. of LBCD at Aintha Patri Nalla  (2416003002/WC/10494479) GP 29/07/2022 57887.72 23387.1 56545 33766
331  REAMAL BAGHBAR Const. of LBCD at Dimirikata Nalla  (2416003002/WC/10506969) GP 29/03/2023 59772.43 23916.69 51726 30934.24
332  REAMAL BAGHBAR Const.of Staggered Trench At Ranjana Purnapani  (2416003002/WC/10494463) GP 27/07/2022 214744.56 24255.4 214140 0
333  REAMAL BAGHBAR Const.of Staggered Trench At Belamunda  (2416003002/WC/10494457) GP 27/07/2022 214744.56 24255.4 221020 0
334  REAMAL BAGHBAR Const.of Staggered Trench At Ghantrabila  (2416003002/WC/10494458) GP 27/07/2022 214744.56 24255.4 218010 5000
335  REAMAL BAGHBAR Const.of Staggered Trench At Baghbar  (2416003002/WC/10494460) GP 27/07/2022 214744.56 24255.4 210270 0
336  REAMAL BUDHAPAL LBCD on Hrudapali Nalla  (2416003003/WC/10432250) GP 27/03/2023 22285.72 12429.62 21312 15819.99
337  REAMAL BUDHAPAL LBCD On Surungipal Nalla  (2416003003/WC/10432251) GP 05/07/2022 22293.5 12420.26 23598 5028
338  REAMAL BUDHAPAL LBCD on Gariapali Nalla  (2416003003/WC/10432252) GP 17/10/2022 22293.5 12420.26 27324 12028
339  REAMAL BUDHAPAL LBCD Surungipal Nalla  (2416003003/WC/10489111) GP 27/03/2023 23155.9 11353.81 21312 15819.99
340  REAMAL BUDHAPAL LBCD Thinal Nalla  (2416003003/WC/10489127) GP 27/03/2023 23155.9 11353.81 21312 15819.99
341  REAMAL BUDHAPAL LBCD Budhapal Nala  (2416003003/WC/10439280) GP 05/08/2022 33439.48 18694.14 37260 22056
342  REAMAL BUDHAPAL LBCD on Thinal Nalla  (2416003003/WC/10432249) GP 26/07/2022 44587.01 24839.52 52164 7056
343  REAMAL BUDHAPAL LBCD Budhapal Nalla  (2416003003/WC/10489118) GP 27/03/2023 50778.7 17182.17 48840 23160.26
344  REAMAL BUDHAPAL LBCD Natripal Nalla  (2416003003/WC/10489364) GP 27/03/2023 63981.16 20849.32 61272 28885.39
345  REAMAL BUDHAPAL LBCD Salarpal Nalla  (2416003003/WC/10489369) GP 31/01/2023 63981.16 20849.32 47952 28183.39
346  REAMAL BUDHAPAL Staggered Trench Thinal  (2416003003/WC/10432222) GP 17/10/2022 113428.69 8571.53 114885 13112
347  REAMAL BUDHAPAL Strenger Trench at Budhapal  (2416003003/WC/10432240) GP 05/04/2022 113428.69 8571.53 112194 5000
348  REAMAL BUDHAPAL Staggered Trench at Natripal  (2416003003/WC/10432225) GP 17/10/2022 113428.69 8589.53 114264 13112
349  REAMAL BUDHAPAL Staggered trench Gadiapal  (2416003003/WC/10489055) GP 27/03/2023 226264.21 17735.6 223332 13450
350  REAMAL BUDHAPAL Staggered Trench Thinal  (2416003003/WC/10489067) GP 27/03/2023 226264.21 15712.6 228330 10000
351  REAMAL BUDHAPAL Starggered Trench Salarpal  (2416003003/WC/10489092) GP 27/03/2023 226632.12 17368.28 221778 13450
352  REAMAL BUDHAPAL Staggered Trench Surungipal  (2416003003/WC/10489042) GP 27/03/2023 226264.21 17735.6 209346 9020
353  REAMAL BUDHAPAL StaggerTrench Gariapali  (2416003003/WC/10489050) GP 05/04/2022 226264.21 17735.6 203604.98 5000
354  REAMAL BUDHAPAL Staggered Trench Budhapal  (2416003003/WC/10489060) GP 05/08/2022 226264.21 17735.6 226180 5000
355  REAMAL BUDHAPAL Starggerd Trench Sendha  (2416003003/WC/10489070) GP 05/04/2022 226264.21 17735.6 233920 5000
356  REAMAL BUDHAPAL Starggered Trench Juradanga  (2416003003/WC/10489074) GP 05/08/2022 226264.21 17735.6 224030 5000
357  REAMAL BUDHAPAL Starggered Trench Telipasi  (2416003003/WC/10489080) GP 05/04/2022 226264.21 17735.6 193715 5000
358  REAMAL BUDHAPAL Starggered Trench Bipragrubahal  (2416003003/WC/10489088) GP 05/04/2022 225896.3 18103.92 220805 5000
359  REAMAL BUDHAPAL Starggered Trench Natripal  (2416003003/WC/10489098) GP 06/04/2022 226264.21 17735.6 237790 5000
360  REAMAL BUDHAPAL Biprabrubahal New Bandha  (2416003003/WC/10455452) GP 05/12/2022 479507.13 20493.09 193070 5000
361  REAMAL BUDIDO Const of Staggered Trench at Medinipur  (2416003004/WC/10494920) GP 16/08/2022 228921.34 15078.67 175440 0
362  REAMAL BUDIDO Construction of staggered trench at Barapali  (2416003004/WC/10495911) GP 12/04/2022 228921.34 15078.67 203820 0
363  REAMAL BUDIDO Construction of Staggered trench at Ratankhalinali  (2416003004/WC/10495912) GP 16/08/2022 228921.34 15078.67 221450 6318
364  REAMAL BUDIDO Construction of staggered Trench at Madhapali  (2416003004/WC/10496009) GP 12/04/2022 228921.34 15078.67 208980 0
365  REAMAL BUDIDO Construction of staggered Trench at sindhupali  (2416003004/WC/10496010) GP 16/08/2022 228921.34 15078.67 201240 6318
366  REAMAL BUDIDO Const of Staggered Trench at Iswarpali  (2416003004/WC/10494918) GP 16/08/2022 343382 21417.99 324435 8424
367  REAMAL GUNDIAPALI CONST OF STAGGERED TRENCH AT BUDHIKUTUNI  (2416003006/WC/10496025) GP 24/09/2022 218020.32 25980.16 214355 10530
368  REAMAL GUNDIAPALI Renovation of Dhauraghot Village Pond  (2416003006/WC/10402927) GP 24/08/2022 381448.69 17054.2 214959 8112
369  REAMAL KANTABAHAL RENOVATION OF BRAHMANPALI RANGIA KATA  (2416003007/WC/10409927) GP 09/06/2022 237259.26 58179.23 202500 6084
370  REAMAL KANTABAHAL CONST. OF STRAGGERED TRENCH AT KANTABAHAL  (2416003007/WC/10490298) GP 08/08/2022 456567.25 26432.58 436020 19742
371  REAMAL KANTABAHAL ONST .OF STRAGGERED TRENCH AT JAMBUNALI  (2416003007/WC/10490302) GP 08/08/2022 456567.25 26432.58 402480 21848
372  REAMAL KANTABAHAL RENOVATION OF BRAHMANPALI NUA KATA  (2416003007/WC/10398150) GP 31/10/2022 465540.56 34132.35 469602 15000
373  REAMAL KANTABAHAL RENOVATION OF BRAHMANPALI MAJHI KATA  (2416003007/WC/10398151) GP 31/10/2022 481687.78 18316.24 477846 13316
374  REAMAL KANTABAHAL RENOVATION OF BRAHMANPALI KHALI KATA  (2416003007/WC/10398152) GP 31/10/2022 481687.78 17929.24 478584 13316
375  REAMAL KANTABAHAL Const of check dam $ canalling System at Brahmanpali  (2416003007/WC/10450815) GP 05/12/2022 98818.1 779490.53 98568 789859.6927
376  REAMAL KARLAGA Const of Staggered Trench at Dudukajharan Reserve hill  (2416003008/WC/10436292) GP 14/11/2022 169111.86 11761.48 168276 0
377  REAMAL KARLAGA Const of Gabion structure on Kapagola Nalla( 7 nos)  (2416003008/WC/10427778) GP 31/10/2022 91473.08 61591.03 29808 70194
378  REAMAL KARLAGA Imp of Karlaga Kata  (2416003008/WC/10525060) GP 10/08/2022 291863.92 200422.07 275724 103506.8232
379  REAMAL KARLAGA IMP.OF KHANDIA BANDHA  (2416003008/WC/10415332) GP 10/08/2022 299645.82 190398.88 285492 177521.2041
380  REAMAL KARLAGA BEAUTIFICATION OF SIPUR NUA BANDHA  (2416003008/WC/10415437) GP 15/08/2022 116973.01 352492.26 117576 369784.9872
381  REAMAL KARLAGA Imp of Babu Kata  (2416003008/WC/10525054) GP 06/12/2022 291863.92 200422.07 289488 132043.6082
382  REAMAL KARLAGA Imp of Sipur Padan Kata  (2416003008/WC/10463695) GP 10/08/2022 473134.38 26866.25 456088 7656
383  REAMAL KARLAGA const of Checkdam at Kapagola  (2416003008/WC/10538780) GP 10/08/2022 135687.12 749517.92 143856 685024.9974
384  REAMAL KHILEI LBCD at Matha ghagi nalla  (2416003009/WC/10501788) GP 21/06/2022 57887.72 27087.37 77400 0
385  REAMAL KHILEI LBCD at Taleisar nalla  (2416003009/WC/10501796) GP 19/10/2022 57899.84 27171.56 79980 4056
386  REAMAL KHILEI Const. of Staggered Trench at Taleisar  (2416003009/WC/10434138) GP 12/04/2022 228919.72 15080.28 229842 11478
387  REAMAL KHILEI Staggered trench Khairapali  (2416003009/WC/10501739) GP 19/10/2022 224424.67 19575.33 223600 8112
388  REAMAL KHILEI Staggered trench Khilei Nuakata side  (2416003009/WC/10501776) GP 21/06/2022 224424.67 19575.33 229620 0
389  REAMAL KHILEI Staggered trench Siarimalia  (2416003009/WC/10501779) GP 19/10/2022 224424.67 19575.33 224675 13112
390  REAMAL KHILEI Staggered trench Taleisar  (2416003009/WC/10501783) GP 13/11/2022 224424.67 19575.33 98040 0
391  REAMAL KHILEI Staggered trench Khilei Dam side  (2416003009/WC/10504412) GP 21/06/2022 224424.67 19575.33 228330 0
392  REAMAL KUNDHEIGOLA Const of Staggered Trench at Koradapasi  (2416003010/WC/10496013) GP 02/11/2022 109555.21 12444.53 110080 5000
393  REAMAL KUNDHEIGOLA Const of Staggered Trench at Panchamahala  (2416003010/WC/10434841) GP 03/11/2022 106974.04 12025.97 107070 11318
394  REAMAL KUNDHEIGOLA Const of Staggered Trench at Kundheigola  (2416003010/WC/10498941) GP 12/04/2022 109555.21 10595.53 109650 6800
395  REAMAL KUNDHEIGOLA Const of LBCD on Chikanghati Nalla   (2416003010/WC/10571551) GP 29/03/2023 119544.87 46832.38 118104 60410.48
396  REAMAL KUNDHEIGOLA Const of LBCD on Khandadhua Nalla  (2416003010/WC/10496017) GP 12/04/2022 129649.9 37368.89 131580 66339
397  REAMAL LULANG Const of Staggered Trench at Lulang  (2416003011/WC/10434833) GP 02/11/2022 226857.38 17142.62 228330 12852
398  REAMAL LULANG Const of Staggered Trench at Lugapuda  (2416003011/WC/10434835) GP 10/08/2022 226857.38 17142.62 225750 13424
399  REAMAL MAHALEIPADA Const. of LBCD at Badsimloi  (2416003012/WC/10505583) GP 02/11/2022 60934.44 24618.28 65790 31646
400  REAMAL MAHALEIPADA Const of LBCD at Sansimloi  (2416003012/WC/10505611) GP 12/05/2022 60934.44 24618.28 61920 36114
401  REAMAL MAHALEIPADA Community Dugwell at Rajamunda Matha  (2416003012/WC/10478579) GP 12/02/2023 62183.52 58436.88 40232 50171.2888
402  REAMAL MAHALEIPADA Const.Of Staggered Trench at Belguth  (2416003012/WC/10493965) GP 02/11/2022 222773.16 19227.69 203820 20136
403  REAMAL MAHALEIPADA Const. of Staggered Trench at Badsimloi  (2416003012/WC/10493969) GP 05/04/2022 222773.16 19227.69 210915 21742
404  REAMAL NAULIPADA Staggered trench at Nutan Debichuan  (2416003013/WC/10497946) GP 14/04/2022 284516.52 14163.11 283155 13424
405  REAMAL NAULIPADA Staggered trench at Sunaripada  (2416003013/WC/10497950) GP 14/04/2022 343382 21069.75 344215 17636
406  REAMAL NAULIPADA Staggered trench at Tileipasi  (2416003013/WC/10497948) GP 20/08/2022 398977.19 25837.69 404630 17636
407  REAMAL NAULIPADA Staggered trench at Madhupali  (2416003013/WC/10497925) GP 14/04/2022 457842.67 26426.34 464830 17636
408  REAMAL NUADIHI LBCD at Nuadihi nalla  (2416003014/WC/10491156) GP 19/08/2022 63981.16 20849.32 79980 12304
409  REAMAL NUADIHI LBCD at Pudadihi nalla  (2416003014/WC/10491218) GP 19/08/2022 63981.16 20849.32 79980 9056
410  REAMAL NUADIHI LBCD at Fuljhari  (2416003014/WC/10491287) GP 19/08/2022 63981.16 20849.32 79980 9056
411  REAMAL NUADIHI Connst of Gabion Structure on Padianali Nalla  (2416003014/WC/10428112) GP 03/08/2022 36549.11 75550.12 39744 59492
412  REAMAL NUADIHI Const.of Gabion Structure on Andharikhol Munsimunda Nalla  (2416003014/WC/10429061) GP 29/03/2023 36241.24 75858.54 35742 85079.8
413  REAMAL NUADIHI Const. of Staggered Trench at Sankarpur  (2416003014/WC/10434037) GP 19/08/2022 113428.69 8571.53 113220 9056
414  REAMAL NUADIHI Const. of Staggered Trench at Bhejikudar  (2416003014/WC/10434042) GP 29/10/2022 113428.69 8571.53 115512 5000
415  REAMAL NUADIHI Staggered Trench Nuadihi  (2416003014/WC/10491150) GP 19/08/2022 226877.4 17122.73 225750 5000
416  REAMAL NUADIHI Staggered trench at Bhejikudar  (2416003014/WC/10491247) GP 03/08/2022 226877.4 17122.73 172860 0
417  REAMAL NUADIHI Staggered Trench Malarbahal  (2416003014/WC/10491160) GP 19/08/2022 347980.87 18018.74 330240 14126
418  REAMAL NUADIHI Staggered trench at Mahasindhu  (2416003014/WC/10491222) GP 19/08/2022 347980.87 18018.74 299280 13112
419  REAMAL NUADIHI Imp. of Ballamunda Kata  (2416003014/WC/10405168) GP 19/08/2022 475809.66 24193.46 473040 19706
420  REAMAL PALSAMA Const of LBCD on Ambkhol Nala  (2416003015/WC/10494388) GP 30/03/2023 38385.46 10013.52 35964 18167
421  REAMAL PALSAMA Const of LBCD on Jualibhanga Nala  (2416003015/WC/10494390) GP 10/10/2022 63981.16 20297.32 65340 0
422  REAMAL PALSAMA Const of LBCD on Dalbeheramunda Jamjharan Nala  (2416003015/WC/10494391) GP 20/07/2022 63981.16 20849.32 65760 0
423  REAMAL PALSAMA Const of LBCD on Dhiramunda Budhia Nala  (2416003015/WC/10494392) GP 20/07/2022 63981.16 20849.32 78828 0
424  REAMAL PALSAMA Const of LBCD on Dhiramunda Charigharia Nala  (2416003015/WC/10494393) GP 20/07/2022 63981.16 20849.32 74790 0
425  REAMAL PALSAMA Const of LBCD on Chhatripita Haldiakhol Nala  (2416003015/WC/10494394) GP 20/07/2022 63981.16 20849.32 81240 0
426  REAMAL PALSAMA Const of Staggered Trench at Palsama  (2416003015/WC/10431886) GP 20/07/2022 226857.38 17143.06 227198 0
427  REAMAL PALSAMA Const of Staggered Trench at Ambakhol  (2416003015/WC/10431980) GP 26/10/2022 226857.38 17143.06 107796 0
428  REAMAL PALSAMA Const of Staggered Trench at Chhatripita  (2416003015/WC/10431983) GP 20/07/2022 226857.38 17143.06 228636 0
429  REAMAL PALSAMA Const of Staggered Trench at Dhiramunda  (2416003015/WC/10431984) GP 20/07/2022 226857.38 17143.06 226224 0
430  REAMAL PALSAMA Const of Staggered Trench at Jualibhanga  (2416003015/WC/10431986) GP 20/07/2022 226857.38 17143.06 227964 0
431  REAMAL PALSAMA Const of Staggered Trench at Dalabeheramunda  (2416003015/WC/10431989) GP 20/07/2022 226857.38 17143.06 227168 0
432  REAMAL PALSAMA Renovation of village Pond One  (2416003015/WC/10412977) GP 10/08/2022 235045.21 14956.63 113520 0
433  REAMAL PALSAMA Imp of Ghodanali Kata  (2416003015/WC/10408453) GP 10/08/2022 472420.48 27583.56 294330 0
434  REAMAL PALSAMA Imp of Mahadev Kata  (2416003015/WC/10408463) GP 10/06/2022 475809.66 24193.46 329433 0
435  REAMAL PALSAMA Imp of Dehuripal Kata  (2416003015/WC/10418117) GP 20/10/2022 323998.59 164814.5 191154 0
436  REAMAL PARA Const of Gabion Stracture on Ambachua Pahad Nallha  (2416003016/WC/10428492) GP 03/11/2022 27177.82 56897.24 29808 34696
437  REAMAL PARA Const of Gabion Stracture on Tipeijharan Matha Nallha  (2416003016/WC/10428490) GP 13/04/2022 27177.82 56897.24 28152 41786
438  REAMAL PARA Const of Gabion Stracture on Dahi Nallha  (2416003016/WC/10428497) GP 03/11/2022 36241.24 75858.54 49680 39267
439  REAMAL PARA Const. of Staggered Trench at Para Rangamatia  (2416003016/WC/10432409) GP 08/04/2022 113428.69 8571.53 96669 5000
440  REAMAL PARA Const. of Staggered Trench at Para Belahuli  (2416003016/WC/10432414) GP 08/04/2022 113428.69 8571.53 109296 5000
441  REAMAL PARA Const. of Staggered Trench at Ambachua kata  (2416003016/WC/10432658) GP 08/04/2022 113428.69 8571.53 92943 5000
442  REAMAL PARA Const.of Staggered Trench at Belahuli  (2416003016/WC/10494624) GP 19/08/2022 226877.4 17122.73 213065 11318
443  REAMAL PARA StaGgered Trencj at Baliakha  (2416003016/WC/10494627) GP 19/08/2022 226877.4 17122.73 231125 11318
444  REAMAL PARA Staggeref Trench at Jhuturigunja  (2416003016/WC/10494629) GP 19/08/2022 226877.4 17122.73 229620 11318
445  REAMAL PARA Staggered Trench at Talbahali  (2416003016/WC/10494673) GP 19/08/2022 226877.4 17122.73 231555 11318
446  REAMAL PARA Const.of Staggered Trench at Rutanali  (2416003016/WC/10494692) GP 19/08/2022 226877.4 17122.73 223170 11318
447  REAMAL REAMAL Const of LBCD on Reamal Nalla  (2416003017/WC/10498322) GP 10/08/2022 60312.66 22887.54 59340 37166
448  REAMAL REAMAL Const of LBCD at Timur Nalla  (2416003017/WC/10498327) GP 10/08/2022 60437.02 23034.07 57620 35546
449  REAMAL REAMAL Const of Stragged Trench at Badbahal  (2416003017/WC/10498323) GP 21/06/2022 228921.34 13607.17 224030 5000
450  REAMAL REAMAL Const of Stragged Trench at Darjimunda  (2416003017/WC/10498324) GP 21/06/2022 228921.34 13607.17 231770 5000
451  REAMAL REAMAL Const of Staggered Trench at Timur  (2416003017/WC/10498325) GP 21/06/2022 228921.34 13607.17 227900 5000
452  REAMAL TABADA STAGGERED TRENCH AT TABADA  (2416003018/WC/10495103) GP 02/03/2023 227286.18 15772.82 224890 12732
453  REAMAL TARANGE Const.of Straggered Trench at Harapali(1hec.)  (2416003019/WC/10433461) GP 13/04/2022 113428.69 8571.53 109005 7000
454  REAMAL TARANGE Const of Staggered Trench at Sampali   (2416003019/WC/10489072) GP 13/04/2022 217475.27 22834.71 228115 7000
455  REAMAL TARANGE Const of Staggered Trench at Narashinghataila   (2416003019/WC/10489085) GP 13/04/2022 217679.66 22836.75 221880 17440
456  REAMAL TARANGE Const of Staggered Trench at Khalidhipa   (2416003019/WC/10489096) GP 13/12/2022 225344.44 18655.4 203820 0
457  REAMAL TARANGE Const of Staggered Trench at Kumal  (2416003019/WC/10489102) GP 28/03/2023 225344.44 18655.4 224220 5000
458  REAMAL TARANGE Const of Staggered Trench at Baghamari   (2416003019/WC/10489106) GP 28/03/2023 225344.44 18655.4 194790 0
459  REAMAL TARANGE Const of Staggered Trench at Tarang  (2416003019/WC/10489034) GP 28/03/2023 227932.06 15078.85 225552 5000
460  REAMAL TARANGE Imp.of Kumal Hatakhol canal  (2416003019/WC/10451983) GP 30/03/2023 138524.72 138857.97 163116 136775.5125
461  REAMAL TARANGE Beautification of Pond at Swalpaghati Kata  (2416003019/WC/10451979) GP 13/04/2022 468224.6 29775.24 474720 18440
462  REAMAL TARANGE Imp of Kumal Bada Kata  (2416003019/WC/10465815) GP 10/11/2022 307006.26 185783.03 310890 181322.4035
463  REAMAL TARANGE Imp.of Kumal Nayak Bandha   (2416003019/WC/10474987) GP 30/03/2023 329639.5 163222.26 201240 167389.0345
464  REAMAL TINKBIR Imp of Khadinali Kata   (2416003020/WC/10458772) GP 12/04/2022 240739.95 229467.94 239940 255058.231
465  REAMAL TINKBIR Beautification of pond at Rajabandha Tinkbir   (2416003020/WC/10451991) GP 07/11/2022 142517.92 332254.67 193500 195863.7683
466  REAMAL TUHILAMAL Const of LBCD on Hitam Nallha  (2416003021/WC/10433067) GP 28/04/2022 63067.15 21977.37 62928 21852
467  REAMAL TUHILAMAL Const of Staggered Trench At Kendunali  (2416003021/WC/10494201) GP 25/03/2023 222773.16 19755.69 213342 18928
468  REAMAL TUHILAMAL Const of Staggered Trench At Jadagola  (2416003021/WC/10494202) GP 19/10/2022 222773.16 19755.69 223600 17836
469  REAMAL TUHILAMAL Const of Staggered Trench At Pathuripal  (2416003021/WC/10494204) GP 14/02/2023 222773.16 19755.69 222740 17636
470  REAMAL TUHILAMAL Const of Staggered Trench At Nuataila  (2416003021/WC/10494205) GP 19/10/2022 222773.16 19755.69 222310 17636
471  REAMAL TUHILAMAL Const of Staggered Trench At Nilgandiapal  (2416003021/WC/10494206) GP 16/03/2023 222773.16 19755.69 222740 13424
472  REAMAL TUHILAMAL Const of Staggered Trench At Khariakani  (2416003021/WC/10494208) GP 19/10/2022 222773.16 19755.69 214140 17636
473  REAMAL TUHILAMAL Const of Staggered Trench At Kukutinali  (2416003021/WC/10494203) GP 19/10/2022 449830.43 34554.22 456660 23954
474  REAMAL TUHILAMAL Improvement of Jadagola WHS  (2416003021/WC/10475908) GP 28/10/2022 138746.59 333759.35 129000 361286.9308
475  REAMAL UTUNIA Const of LBCD At Godamal Nalla  (2416003022/WC/10435583) GP 01/06/2022 63067.15 21977.37 68310 0
476  REAMAL UTUNIA Const of LBCD on Hadsanhar  (2416003022/WC/10435587) GP 09/08/2022 63067.15 21977.37 68103 26056
477  REAMAL UTUNIA Const.of Staggered Trench At Bisalataila  (2416003022/WC/10491100) GP 01/06/2022 218020.32 25980.16 224460 0
478  REAMAL UTUNIA Const.of Staggered Trench At Bhandipathar  (2416003022/WC/10491104) GP 01/06/2022 218020.32 25980.16 203820 0
479  REAMAL UTUNIA Const.of Staggered Trench At Hariharpur  (2416003022/WC/10491109) GP 01/06/2022 218020.32 25980.16 205540 0
480  REAMAL UTUNIA Const.of Staggered Trench At Hadsanhar Colony Sahi  (2416003022/WC/10491114) GP 04/04/2022 227286.18 16713.82 224460 0
481  REAMAL UTUNIA Const.of Staggered Trench At Talkudar  (2416003022/WC/10491117) GP 04/04/2022 218020.32 25980.16 234780 0
482  REAMAL UTUNIA Const.of Staggered Trench At Tapataila  (2416003022/WC/10491095) GP 01/06/2022 462952.52 25047.43 418390 0
483  REAMAL UTUNIA Const.of Staggered Trench At Godamal Nursery  (2416003022/WC/10491097) GP 04/04/2022 462952.52 25047.43 448920 0
484  REAMAL UTUNIA Const.of Staggered Trench At Dhaurakhaman  (2416003022/WC/10491107) GP 01/06/2022 462952.52 25047.43 393020 0
485  REAMAL UTUNIA Check Dam at Goudanali  (2416003022/WC/10465544) GP 18/08/2022 281742.09 573460.13 233490 496345.808
486  REAMAL TENTALABAHAL Const. of Staggred Trench at Rengalnali  (2416003023/WC/10434247) GP 08/08/2022 110596.9 11403.1 110176 6760
487  REAMAL TENTALABAHAL STAGGERED TRENCH AT RENGALNALI  (2416003023/WC/10494519) GP 28/10/2022 109555.21 12444.79 109368 0
488  REAMAL TENTALABAHAL CONST. OF STAGGERED TRENCH AT KENDUGHAT  (2416003023/WC/10434024) GP 08/08/2022 228002.19 15997.81 212052 12480
489  REAMAL TENTALABAHAL Const. of Staggred Trench at Sadhupali  (2416003023/WC/10434248) GP 08/08/2022 227059.56 16940.44 213150 14196
490  REAMAL TENTALABAHAL Const.of Staggred Trench at Tentalabahal  (2416003023/WC/10434251) GP 02/01/2023 227059.56 16940.44 226590 10596
491  REAMAL TENTALABAHAL STAGGERED TRENCH AT KENDUGHAT  (2416003023/WC/10494514) GP 08/08/2022 218129.33 24670.67 228330 8424
492  REAMAL TENTALABAHAL STAGGERED TRENCH AT BARKANI  (2416003023/WC/10494520) GP 08/08/2022 225651.03 18348.97 194145 12371
493  REAMAL TENTALABAHAL STAGGERED TRENCH AT BILEINALI  (2416003023/WC/10494522) GP 13/12/2022 227286.18 16713.82 227171 0
494  REAMAL TENTALABAHAL STAGGERED TRENCH AT DALAKBAHAL  (2416003023/WC/10494515) GP 02/01/2023 336841.39 28958.61 336766 8472
495  REAMAL TENTALABAHAL STAGGERED TRENCH AT SADHUPALI  (2416003023/WC/10494523) GP 02/01/2023 336841.39 29158.61 332330 12636
496  REAMAL TENTALABAHAL STAGGERED TRENCH AT KUNDAJHARI  (2416003023/WC/10494525) GP 02/08/2022 336841.39 29158.61 338410 12684
497  REAMAL TUNGAMAL LBCD on Jharadiha Nala  (2416003025/WC/10439510) GP 25/03/2023 63067.15 22096.96 63048 35197.35
498  REAMAL TUNGAMAL LBCD on Kanjiamb Nallah  (2416003025/WC/10439698) GP 31/10/2022 63067.15 22096.96 22356 22062
499  REAMAL TUNGAMAL LBCD on Badjharan nallah  (2416003025/WC/10439700) GP 31/10/2022 63067.15 22096.96 24840 22062
500  REAMAL TUNGAMAL Constn of Straggered Strench at Tungamal  (2416003025/WC/10441154) GP 03/06/2022 228002.19 15997.81 209934 0
501  REAMAL TUNGAMAL Const of Staggered Trench at Gurujang  (2416003025/WC/10498244) GP 08/04/2022 459886.61 25258.77 483750.72 0
502  REAMAL NUAPADA Constn of Comm.Dugwell at Aunli Kandhasahi   (2416003026/WC/10495863) GP 25/03/2023 54708.71 99869.33 61272 96969.1949
503  REAMAL NUAPADA Constn of Comm.Dugwell at Aunli Ghasisahi  (2416003026/WC/10495864) GP 25/03/2023 54708.71 99869.33 61272 96969.1949
504  REAMAL NUAPADA Constn of Comm.Dugwell at Nuapada Harijansahi  (2416003026/WC/10495866) GP 25/03/2023 54708.71 99869.33 61272 96969.1949
Report Completed Excel View