Asset Register
|
Work Name
|
(MTN/40/7264) तालाब निर्माण गहरा वेस्ट वियर मय पिचिंग मदनपुरा |
Nature of Work |
Water Conservation
|
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Derelict |
Sunken Pond |
|
Location
|
Start Location |
मदनपुरा |
Khata No. |
Plot No. |
|
|
|
Sanction No. and Sanction Date
: 2822-30 ,
01/03/2009
|
Whether Included in Five Year Perspective Plan
: No |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
12.951
|
Estimated Completion Time (in Months)
|
6 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
0 |
0 |
0 |
2300 |
0 |
2300 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1122 |
102 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
42425(3740),42426(2244),42427(3366),42428(2244),42429(3366), 42430(1870),42431(3366),42432(2244),42433(3366),42434(2992), 42435(2244),42436(1870),42437(2244),42438(2992),
|
Work start date |
16/06/2010 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|
MB Book Detail
|