Asset Register
|
Work Name
|
(2732002044/JPN/48/5906) Bharat Nirman Rajeev Gandhi Sewa Kendra,गागरोन |
Nature of Work |
|
Work Status
|
Completed
|
Work Purpose status
|
New Construction |
Scope of Work
|
|
Sanction No. and Sanction Date
: 8743-48 ,
29/03/2010
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
13.48637
|
Estimated Completion Time (in Months)
|
6 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
43266 |
27171 |
28771 |
1048183.2 |
0 |
1147391.2 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
798 |
111 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
15291(950),15292(396),15896(5238),15897(2600),1000656(400), 1000739(4200),1000912(3000),1001103(6400),1001394(3927),1001729(6307), 1001730(1309),1001862(2142),1002234(3780),27320020441002803(2023),27320020441100029(476), 27320020441100030(7259),27320020441100031(1904),27320020441100082(5184),27320020441100084(400),27320020441100147(3441), 27320020861101088(6380),27320020861101309(4500),27320020861101565(7735),27320020861101776(3465),27320020861102123(2522),
|
Work start date |
01/04/2010 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|
MB Book Detail
|