Asset Register
|
Work Name
|
(0550008002/IC/03/08-09) मिसार खां के घर से छोटी खडहुई तक सिंचाई नाला |
Nature of Work |
|
|
Completed
|
Scope of Work
|
|
Location
|
|
Sanction No. and Sanction Date
: 03/08-09 ,
07/01/2009
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
4.502
|
Estimated Completion Time (in Months)
|
3 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
31506 |
0 |
0 |
0 |
0 |
31506 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
354 |
60 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
193973(4272),193974(1602),193975(4272),193976(1602),193977(4272), 193978(1602),193979(4272),193980(445),384996(4272),384997(1602), 386548(3293),
|
Work start date |
25/12/2008 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|