Asset Register
|
Work Name
|
(2732002058/WC/JPN48/1837) गॉंवडी तालाब खुदाई एवं विकास कार्य |
Nature of Work |
Water Conservation
|
Work Status
|
Completed
|
Work Purpose status
|
Desilting |
Scope of Work
|
Start Status |
End Status |
Silted |
Desilting |
|
Location
|
Start Location |
सलोतया |
Khata No. |
Plot No. |
|
|
|
Sanction No. and Sanction Date
: 1633-38 ,
21/05/2007
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
10.03
|
Estimated Completion Time (in Months)
|
12 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
0 |
0 |
0 |
40000 |
0 |
40000 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1928 |
177 |
Semi-Skilled |
0 |
0 |
|
88 |
7 |
|
Distinct Number of Muster Rolls used(Amount)
|
151153(0),151154(0),151155(0),151797(0),151798(0), 151799(0),151800(0),151801(0),153048(0),153048(0), 153049(0),153050(0),153051(0),153052(0),172463(0), 172464(0),172465(0),172465(0),172466(0),172467(0), 172468(0),172469(0),172470(0),173489(0),173490(0), 173490(0),173491(0),173492(0),173493(0),173494(0),
|
Work start date |
20/06/2008 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|
MB Book Detail
|