Asset Register
|
Work Name
|
(3001007003/RS/982) Construction RCC IHHL of 68(sixty eight) Nos |
Nature of Work |
|
Work Status
|
Completed
|
Scope of Work
|
|
Sanction No. and Sanction Date
: 5081-5104 ,
05/02/2013
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
3.2776
|
Estimated Completion Time (in Months)
|
1 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
50592 |
23800 |
0 |
253369 |
0 |
327761 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
408 |
68 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
73548(7440),73549(7440),73550(7440),73551(7440),73552(7440), 73553(7440),73554(5952),
|
Work start date |
06/02/2013 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|