Asset Register
|
Work Name
|
(2732001026/AV/112908266360) शमशान घाट निर्माण कार्य चांदपुरा चपलाडा मउबोरदा |
Nature of Work |
|
Work Status
|
Completed
|
Scope of Work
|
|
Sanction No. and Sanction Date
: 11930-36 ,
18/02/2019
|
Whether Included in Five Year Perspective Plan
: |
Whether Work Approved in Annual Plan
: |
Estimated Cost (In Lakhs)
:
8.31
|
Estimated Completion Time (in Months)
|
12 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
0 |
0 |
0 |
0 |
0 |
0 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2232 |
206 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
22039(4680),7786(13350),7787(14790),7788(11060),7789(13524), 7790(16898),7791(12480),7792(14940),7793(13260),7794(20475), 7795(14742),10400(15184),10401(13611),10402(9748),10403(11420), 10404(10497),25183(4320),25184(4536),25185(9735),8794(20320), 8795(20800),8796(19200),8797(18240),8798(6240),19422(6720), 19423(3680),32460(28600),32461(1100),
|
Work start date |
01/04/2019 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|
MB Book Detail
|