Activity | Activity Unit | Activity Quantity | Unit Cost | Total Cost(In Rs.) |
Cement concrete [1:2:4] using 12mm size H.G. Chips including all cost conveyancetaxes,royalit,watering curring, etc. complete |
Cum |
6.6 |
3721.34 |
24560.84 |
Cement concrete [1:4:8] using 40mm sizeB.H.G. metal including all cost conveyancetaxes,royalit,watering curring, etc. complete |
Cum |
6.6 |
2421.86 |
15984.28 |
Earth work exavation in ordinary soil with all lead and lift including rough dressing and breaking of clods to maximum 5 cm to 7 cm and laying in layers not exceeding 0.3 m in depth as per direction of engineer in charge. |
Cum |
6.9 |
107.77 |
743.61 |
Earth work in excavation in foundation including all leads and lifts including rough dressing and breaking clods deposited the excavated materials away from work site. |
cum |
7.05 |
66.1 |
466 |
Earth work in excavation in Hard soil including all leads and lifts including rough dressing and breaking clods deposited the excavated materials away from work site. |
cum |
7.05 |
89.05 |
627.77 |
Filling foundation and plinth with sandincluding all leads and lift watering, rammingcost, conveyance, taxes and royalty etc. |
Cum |
6.6 |
241.39 |
1593.17 |
| | | | |