Activity | Activity Unit | Activity Quantity | Unit Cost | Total Cost(In Rs.) |
Cement concrete with 12 mm size H.G. chips in (1:2:4) |
cum |
61.23 |
579.6 |
35489.78 |
Earth work in hard soil or gravelly soil within all lead and lift including rough dressing and breaking clods to maximum 5 cm to 7 cm and laying in layers not exceeding 0.3 m in depth and as per the direction of engineer-in-charge. |
Cum |
132.97 |
89.05 |
11840.7 |
Earth work in ordinary soil all lead and lift including rough dressing and breaking of clods to maximum 5 cm to 7 cm and laying in layers not exceeding 0.3 m in depth as per direction of engineer in charge. |
cum |
198.14 |
71.73 |
14212.48 |
Filling in foundation and plinth with sand watered and rammed |
cum |
69.22 |
15.57 |
1077.77 |
| | | | |