Activity | Activity Unit | Activity Quantity | Unit Cost | Total Cost(In Rs.) |
Cement concrete [1:2:4] using 12mm size H.G. Chips including all cost conveyancetaxes,royalit,watering curring, etc. complete |
Cum |
0.94 |
579.6 |
544.82 |
Cement concrete [1:3:6] using 40mm sizeB.H.G. metal including all cost conveyancetaxes,royalit,watering curring, etc. complete |
Cum |
20.1 |
491.4 |
9877.14 |
Cement concrete [1:4:8] using 40mm sizeB.H.G. metal including all cost conveyancetaxes,royalit,watering curring, etc. complete |
Cum |
6.65 |
491.4 |
3267.81 |
Earth work in excavation in foundation in hard soil including all leads and lifts including rough dressing and breaking clods deposited the excavated materials away from work site. |
cum |
60.55 |
108.99 |
6599.34 |
Filling foundation and plinth with sandincluding all leads and lift watering, rammingcost, conveyance, taxes and royalty etc. |
Cum |
1.23 |
15.88 |
19.53 |
R.C.C [1:1.5:3] using 12mm size B.H.G.chips including all cost conveyance hoisting laying taxes,royalit,watering curring, & centering shuttering etc.excluding costof iron rod . |
Cum |
3.13 |
579.6 |
1814.15 |
| | | | |