Bill No. |
Bill Date (DD/MM/YYYY |
Material |
Total Amount (In Rupees) |
Amount Paid (In Rupees) |
332 |
22/07/2021 |
0293-Stone Aggregate(single size): 40 mm nominal size |
18107.5986 |
18107.5986 |
332 |
22/07/2021 |
0295-Stone Aggregate(single size):20 mm nominal size |
10430.4 |
10430.4 |
332 |
22/07/2021 |
0297-Stone Aggregate(single size): 10 mm nominal size |
7324.8 |
7324.8 |
332 |
22/07/2021 |
0982-Coarse sand (zone III) |
536.7968 |
536.7968 |
332 |
22/07/2021 |
0983-Fine sand (zone IV) |
1091.4525 |
1091.4525 |
332 |
22/07/2021 |
2202-Stone aggregate below 40 mm nominal size |
5892.1551 |
5892.1551 |
332 |
22/07/2021 |
2203-Coarse sand |
4007.2228 |
4007.2228 |
332 |
22/07/2021 |
2206-Stone aggregate 40 mm nominal size and above |
3979.7511 |
3979.7511 |
332 |
22/07/2021 |
2209-Cement |
1541.812 |
1541.812 |
332 |
22/07/2021 |
2335-Jamuna sand |
9016.2513 |
9016.2513 |
332 |
22/07/2021 |
MR8003-Blacksmith(special) |
1360.2 |
1360.2 |
332 |
22/07/2021 |
MR8110-Cement |
49601.4 |
49601.4 |
332 |
22/07/2021 |
MR8111-HYSD bar (Reinforcement) |
1661.5053 |
1661.5053 |
332 |
22/07/2021 |
MR8186-GENERATOR 33KVA |
1460.9 |
1460.9 |
333 |
22/07/2021 |
1198-Second class kail wood in planks |
8240.4624 |
8240.4624 |
333 |
22/07/2021 |
3-Display Board |
2000 |
2000 |
333 |
22/07/2021 |
7335-Binding wire |
537.84 |
537.84 |
333 |
22/07/2021 |
MR8068-Non-sal bullahs 75mm. mean dia of any length. |
1037.25 |
1037.25 |
333 |
22/07/2021 |
MR8111-HYSD bar (Reinforcement) |
43785.8694 |
43785.8694 |
333 |
22/07/2021 |
MR8186-GENERATOR 33KVA |
1450 |
1450 |
333 |
22/07/2021 |
MR8190-CARRIAGE OF WOOD FOR CENTRING & SHUTTERING WORK |
54.855 |
54.855 |
|
|
Total Cash payment(In Rupees) |
173118.5223 |
173118.5223 |