Bill No. |
Bill Date (DD/MM/YYYY |
Material |
Total Amount (In Rupees) |
Amount Paid (In Rupees) |
1 |
10/02/2021 |
10-Miscellaneous /Contingencies charges |
730 |
730 |
1 |
10/02/2021 |
1198-Second class kail wood in planks |
2388 |
2388 |
1 |
10/02/2021 |
2202-Stone aggregate below 40 mm nominal size |
13230.9388 |
13230.9388 |
1 |
10/02/2021 |
2203-Coarse sand |
3093.2668 |
3093.2668 |
1 |
10/02/2021 |
2209-Cement |
22940 |
22940 |
1 |
10/02/2021 |
2265-Carriage of Moorum |
902.8 |
902.8 |
1 |
10/02/2021 |
3-Display Board |
3000 |
3000 |
1 |
10/02/2021 |
7-Worksite facilities/Creche/Drinking water/First aid |
3270 |
3270 |
1 |
10/02/2021 |
Labour Cess |
727 |
727 |
2 |
17/02/2021 |
0296-Stone Aggregate(single size): 12.5 mm nominal size |
8674.704 |
8674.704 |
2 |
17/02/2021 |
10-Miscellaneous /Contingencies charges |
2311 |
2311 |
2 |
17/02/2021 |
1198-Second class kail wood in planks |
9116 |
9116 |
2 |
17/02/2021 |
2202-Stone aggregate below 40 mm nominal size |
9201.168 |
9201.168 |
2 |
17/02/2021 |
2203-Coarse sand |
2016.3702 |
2016.3702 |
2 |
17/02/2021 |
2209-Cement |
27900 |
27900 |
2 |
17/02/2021 |
2265-Carriage of Moorum |
1098 |
1098 |
2 |
17/02/2021 |
7-Worksite facilities/Creche/Drinking water/First aid |
3270 |
3270 |
2 |
17/02/2021 |
Labour Cess |
1184 |
1184 |
2 |
17/02/2021 |
MR8111-HYSD bar (Reinforcement) |
23400 |
23400 |
2 |
17/02/2021 |
MR8190-CARRIAGE OF WOOD FOR CENTRING & SHUTTERING WORK |
7531 |
7531 |
|
|
Total Cash payment(In Rupees) |
145984.2478 |
145984.2478 |