Bill No. |
Bill Date (DD/MM/YYYY |
Material |
Total Amount (In Rupees) |
Amount Paid (In Rupees) |
7278 |
10/10/2022 |
MR8449-Cement |
49500 |
49500 |
7279 |
15/10/2022 |
MR8780-"Mild steel round bar 12 mm dia and below M.S. bars 10mm = 1x1m = 1 metre 1 metre @ 0.60kg/m = 0.60Kg.+ Add wastage @ 5% = 0.03Kg. Total = 0.63 Kg. Say = 0.006 qunital" |
8491.5 |
8491.5 |
7279 |
15/10/2022 |
MR8986-"Flats upto 10 mm thickness M.S. flat 15x3mm = 6x10cm = 0.60 metre 0.6 metre @ 0.35kg/m = 0.21Kg+ Add wastage @ 5% = 0.01 Kg. Total = 0.22 kg = 0.002q." |
15834.15 |
15834.15 |
7587 |
21/10/2022 |
MR8449-Cement |
25200 |
25200 |
7588 |
02/01/2023 |
MR8434-Barbed wireBarbed wire |
23954.94 |
23954.94 |
49 |
10/01/2023 |
MR8727-Sand (Coarse) royalty only (for material part) |
2634.94 |
2634.94 |
49 |
10/01/2023 |
MR8737-Stone for Random Rubble Masonry Royalty only (for material part) |
7082.46 |
7082.46 |
|
|
Total Cash payment(In Rupees) |
132697.99 |
132697.99 |