Bill No. |
Bill Date (DD/MM/YYYY |
Material |
Total Amount (In Rupees) |
Amount Paid (In Rupees) |
25 |
01/04/2019 |
Centering and Shuttering |
4308 |
4308 |
25 |
01/04/2019 |
Semi skilled labour(Stone Pack |
668 |
668 |
51 |
01/04/2019 |
12 mm size HG chips(Hand Broke |
1533.88 |
1533.88 |
51 |
01/04/2019 |
40 mm size HG metal(Hand Broke |
11726.65 |
11726.65 |
51 |
01/04/2019 |
Cost and carriage of sand |
2794.52 |
2794.52 |
96 |
01/04/2019 |
Cement |
21000 |
21000 |
|
|
Total Cash payment(In Rupees) |
42031.05 |
42031.05 |