Bill No. |
Bill Date (DD/MM/YYYY |
Material |
Total Amount (In Rupees) |
Amount Paid (In Rupees) |
02 |
24/03/2021 |
2202-Stone aggregate below 40 mm nominal size |
56380.8 |
56380.8 |
02 |
24/03/2021 |
MR8110-Cement |
122610 |
122610 |
81 |
01/05/2021 |
0296-Stone Aggregate(single size): 12.5 mm nominal size |
2054.3514 |
2054.3514 |
81 |
01/05/2021 |
0982-Coarse sand (zone III) |
3195.2382 |
3195.2382 |
81 |
01/05/2021 |
0983-Fine sand (zone IV) |
18900.9842 |
18900.9842 |
81 |
01/05/2021 |
1198-Second class kail wood in planks |
18706 |
18706 |
81 |
01/05/2021 |
2209-Cement |
80130.4568 |
80130.4568 |
81 |
01/05/2021 |
MR8110-Cement |
9864.049 |
9864.049 |
82 |
01/05/2021 |
0295-Stone Aggregate(single size):20 mm nominal size |
15285.0019 |
15285.0019 |
82 |
01/05/2021 |
0297-Stone Aggregate(single size): 10 mm nominal size |
36893.0835 |
36893.0835 |
82 |
01/05/2021 |
1198-Second class kail wood in planks |
2748 |
2748 |
82 |
01/05/2021 |
2202-Stone aggregate below 40 mm nominal size |
18788.612 |
18788.612 |
82 |
01/05/2021 |
2205-Steel |
109583.936 |
109583.936 |
82 |
01/05/2021 |
8-BFT/TA/Mate |
33060 |
33060 |
82 |
01/05/2021 |
MR8110-Cement |
17376 |
17376 |
83 |
01/05/2021 |
MR8190-CARRIAGE OF WOOD FOR CENTRING & SHUTTERING WORK |
18713 |
18713 |
|
|
Total Cash payment(In Rupees) |
564289.513 |
564289.513 |