Bill No. |
Bill Date (DD/MM/YYYY |
Material |
Total Amount (In Rupees) |
Amount Paid (In Rupees) |
6 |
11/06/2022 |
0982-Coarse sand (zone III) |
1015.1973 |
1015.1973 |
6 |
11/06/2022 |
0983-Fine sand (zone IV) |
3017.1409 |
3017.1409 |
6 |
11/06/2022 |
2202-Stone aggregate below 40 mm nominal size |
16814.7498 |
16814.7498 |
6 |
11/06/2022 |
Labour Cess |
709 |
709 |
6 |
11/06/2022 |
MR8110-Cement |
35207.55 |
35207.55 |
7 |
28/06/2022 |
0297-Stone Aggregate(single size): 10 mm nominal size |
2707.7568 |
2707.7568 |
7 |
28/06/2022 |
0983-Fine sand (zone IV) |
331.19 |
331.19 |
7 |
28/06/2022 |
Labour Cess |
637 |
637 |
7 |
28/06/2022 |
MR8110-Cement |
4023.72 |
4023.72 |
7 |
28/06/2022 |
MR8111-HYSD bar (Reinforcement) |
11101.519 |
11101.519 |
7 |
28/06/2022 |
MR8190-CARRIAGE OF WOOD FOR CENTRING & SHUTTERING WORK |
1741.59 |
1741.59 |
|
|
Total Cash payment(In Rupees) |
77306.4138 |
77306.4138 |