Asset Register
|
Work Name
|
(2732002083/WH/JPN48/134) एनीकट निर्माण नाले पर मोगरा |
Nature of Work |
Water Conservation
|
Work Status
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Non-existent |
Check Dam |
|
Location
|
|
Sanction No. and Sanction Date
: 6935-940 ,
18/02/2006
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
5.345
|
Estimated Completion Time (in Months)
|
34 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
0 |
0 |
0 |
26568 |
0 |
26568 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
1882 |
204 |
Semi-Skilled |
0 |
0 |
|
45 |
6 |
|
Distinct Number of Muster Rolls used(Amount)
|
12213(0),12214(0),12215(0),12216(0),13114(0), 13115(0),13116(0),13117(0),13118(0),33492(0), 33493(0),33494(0),33495(0),123492(0),123493(0), 123494(0),150265(0),150266(0),150267(0),151967(0), 151968(0),151969(0),151970(0),151971(0),153482(0), 153483(0),153484(0),153485(0),153486(0),172786(0), 172786(0),172787(0),172788(0),223791(0),223791(0), 224643(0),224643(0),224644(0),224645(0),224645(0), 227580(0),227580(0),227581(0),227582(0),
|
Work start date |
01/05/2007 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|
MB Book Detail
|